- Home
- JJM-WSS to Arakuzha and Palakkuzha Panch...
JJM-WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District
Project |
JJM-WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District |
Project Code |
EKMJJM092110931 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Now the construction of production components of the new water supply
scheme which is envisaged for distribution of water in Arakuzha and Palakuzha, dividing
the area into 8 different zones is in progress and is nearing completion under the
funding of NABARD. This scheme is having the following components.
1. Intake well : 10 m dia intake well at Moozhi ( Existing)
2. Clear water Pumping Main – 350 mm DI k9 pipe
3. Treatment Plant – 5.5 MLD RSF WTP at Konnanikadu
4. Service Reservoirs
i) 2 LL OHSR at Kumbalathumala for Zone I
ii) 3.5 LL GLSR at Konnanikadu for Zone II
iii) 0.6 LL GLSR at Aroor for Zone III
iv) 1.7 LL GLSR at Achakottimala for Zone IV
v) 1.5 LL GLSR at Illikunnu for Zone V
vi) 1.5 LL GLSR at Elachikunnu for Zone VI
vii) 2.0 LL GLSR at Palanikkumthadam for Zone VII
5. Clear Water Pumping/ Gravity Main
i) 150 mm DI K9 – 4600 m to Zone I
ii) 250 mm DI K9 – 800 m to Zone II
iii) 100 mm DI K9 – 1600 m to Zone III
iv) 150 mm DI K9 – 2850 m to Zone IV
v) 100 mm DI K9 – 2350 m to Zone V
vi) 150 mm DI K9 – 2260 m to Zone VI
vii) 150 mm DI – 2650 m to Zone VII
The distribution system of the scheme is envisaged in Phase II and the
same has to be materialized for the full utilization of the scheme. The works for the
partial commissioning of the scheme is also arranged under State plan |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
366130000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
354000000 |
TS Number |
TS/ 2021-2022/2021/13177 dated 09.12.2021 |
Total Bill Submitted (Rs) |
47344680 |
Total Bill Paid (Rs) |
47344680 |
Population Benefitted |
|
Capacity in MLD |
5.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Arakuzha and Palakuzha Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JJM - WSS to Arakkuzha & Palakkuzha Panchayath - Laying Distribution and Providing FHTC to all house holds-Pandappally Pump house MV Addition - Main Distribution and connected Electrics-General Civil Work |
Project Division Perumbavoor |
|
2 |
WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District |
Project Division Piravom(Kattapana) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Sep 2023 |
80% of work completed.Waiting for PWD cutting sanction for laying pipe. |
Piravom Project Dn AE 1 |
|
24 Aug 2023 |
80% of work completed.Total FHTC to be given - 3243, FHTC given as on 24/08/23 - 1505, HTC given as on 24/8/23 - 15, Waiting for PWD cutting sanction for laying pipe. |
Piravom Project Dn AE 1 |
|
11 Aug 2023 |
Total FHTC to be given - 3243, FHTC given as on 1/08/23 - 1504, HTC given as on 01/8/23 - 15, Waiting for PWD cutting sanction for laying pipe. |
Piravom Project Dn AE 1 |
|
04 Aug 2023 |
Total FHTC to be given - 3243, FHTC given as on 1/08/23 - 1504, HTC given as on 01/8/23 - 15, Waiting for PWD cutting sanction for laying pipe. |
Piravom Project Dn AE 1 |
|
29 Jul 2023 |
Total FHTC to be given - 3243, FHTC given as on 18/7/23 - 1504, HTC given as on 18/7/23 - 15, Waiting for PWD cutting sanction for laying pipe. |
Piravom Project Dn AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/04/2022 |
Scheduled date of Completion of the Project |
20 Apr 2023 |
Expected date of Completion |
20/04/2023 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
09 Dec 2021 |