Jal Jeevan Mission (JJM)-JJM - WSS to Arakkuzha & Palakkuzha Panchayath - Laying Distribution and Providing FHTC to all house holds-Pandappally Pump house MV Addition - Main Distribution and connected Electrics-General Civil Work

Project Jal Jeevan Mission (JJM)-JJM - WSS to Arakkuzha & Palakkuzha Panchayath - Laying Distribution and Providing FHTC to all house holds-Pandappally Pump house MV Addition - Main Distribution and connected Electrics-General Civil Work
Project Code EKMJJM092110931P2
Type Package
Main Project JJM-WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM - WSS to Arakkuzha & Palakkuzha Panchayath - Laying Distribution and Providing FHTC to all house holds-Pandappally Pump house MV Addition - Main Distribution and connected Electrics-General Civil Work
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 190800
TS Number WRD/KWA-CE(CR)/EST_TS/10212/2023_5_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/04/2023
Scheduled date of Completion as per agreement 13 Jul 2023
Expected date of Completion 20/04/2023

Processing Dates

TS Date 01 Jun 2023
Estimate Approval 01 Jun 2023
NIT Approval 01 Jun 2023

Approval Dates

Workorder Date 01 Jun 2023
NA 15 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Piravom Project Dn AE 1
Date: 17/05/2024

Work in progress | 95% Completed

Panel board assembly fabricated and erected by the contractor at pump house room.Install new 250 KVA transformer instead of 160 KVA, by KSEB and charged..

Piravom Project Dn AE 1
Date: 14/05/2024

Work in progress | 95% Completed

Panel board assembly fabricated and erected by the contractor at pump house room.Install new 250 KVA transformer instead of 160 KVA, by KSEB and charged. .