WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District

Project WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District
Project Code EKMJJM092110931P1
Type Package
Main Project JJM-WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Tank and distribution components
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 354000000
TS Number 2021-22/2021/13177
Technical specification OH tank and distribution
Contractor SIBI K JOSE (Mob: 9446928787)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/06/2022
Scheduled date of Completion as per agreement 20 Apr 2023
Expected date of Completion 20/04/2023

Processing Dates

TS Date 09 Dec 2021
Estimate Approval 09 Dec 2021
Tender Closing 19 Apr 2021
Price bid opening 13 Apr 2022

Approval Dates

Workorder Date 21 Apr 2022
NA 27 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Piravom Project Dn AE 1
Date: 17/05/2024

Work in progress | 85% Completed

75.212 km - distribution pipe laying completed at Arakuzha panchayath &150 nos Fhtc given.At palakuzha panchayath- 86.525 km distribution line completed,6.72 km clear water pumping main completed. 1408 nos Fhtcs & 15 nos of HTC given at palakuzha.115 nos of Fhtcs & 10 nos of Htcs given at Arakuzha .Inter connection & leak rectification of Fhtc in progress at palakuzha..

Piravom Project Dn AE 1
Date: 14/05/2024

Work in progress | 85% Completed

75.212 km - distribution pipe laying completed at Arakuzha panchayath &150 nos Fhtc given.At palakuzha panchayath- 86.525 km distribution line completed,6.72 km clear water pumping main completed. 1408 nos Fhtcs & 15 nos of HTC given at palakuzha.115 nos of Fhtcs & 10 nos of Htcs given at Arakuzha .Inter connection & leak rectification of Fhtc in progress at palakuzha. .