Project | WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District |
---|---|
Project Code | EKMJJM092110931P1 |
Type | Package |
Main Project | JJM-WSS to Arakuzha and Palakkuzha Panchayath in Ernakulam District |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Tank and distribution components |
Status | On-going |
District | Ernakulam |
Executing Office | Piravam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 354000000 |
TS Number | 2021-22/2021/13177 |
Technical specification | OH tank and distribution |
Contractor | SIBI K JOSE (Mob: 9446928787) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/06/2022 |
---|---|
Scheduled date of Completion as per agreement | 20 Apr 2023 |
Expected date of Completion | 20/04/2023 |
TS Date | 09 Dec 2021 |
---|---|
Estimate Approval | 09 Dec 2021 |
Tender Closing | 19 Apr 2021 |
Price bid opening | 13 Apr 2022 |
Workorder Date | 21 Apr 2022 |
---|---|
NA | 27 Apr 2022 |
Piravom Project Dn AE 1 |
Date: 17/05/2024 |
Work in progress | 85% Completed
75.212 km - distribution pipe laying completed at Arakuzha panchayath &150 nos Fhtc given.At palakuzha panchayath- 86.525 km distribution line completed,6.72 km clear water pumping main completed. 1408 nos Fhtcs & 15 nos of HTC given at palakuzha.115 nos of Fhtcs & 10 nos of Htcs given at Arakuzha .Inter connection & leak rectification of Fhtc in progress at palakuzha..
Piravom Project Dn AE 1 |
Date: 14/05/2024 |
Work in progress | 85% Completed
75.212 km - distribution pipe laying completed at Arakuzha panchayath &150 nos Fhtc given.At palakuzha panchayath- 86.525 km distribution line completed,6.72 km clear water pumping main completed. 1408 nos Fhtcs & 15 nos of HTC given at palakuzha.115 nos of Fhtcs & 10 nos of Htcs given at Arakuzha .Inter connection & leak rectification of Fhtc in progress at palakuzha. .