Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Sep 2023 80% of work completed.Waiting for PWD cutting sanction for laying pipe. Piravom Project Dn AE 1
24 Aug 2023 80% of work completed.Total FHTC to be given - 3243, FHTC given as on 24/08/23 - 1505, HTC given as on 24/8/23 - 15, Waiting for PWD cutting sanction for laying pipe. Piravom Project Dn AE 1
11 Aug 2023 Total FHTC to be given - 3243, FHTC given as on 1/08/23 - 1504, HTC given as on 01/8/23 - 15, Waiting for PWD cutting sanction for laying pipe. Piravom Project Dn AE 1
04 Aug 2023 Total FHTC to be given - 3243, FHTC given as on 1/08/23 - 1504, HTC given as on 01/8/23 - 15, Waiting for PWD cutting sanction for laying pipe. Piravom Project Dn AE 1
29 Jul 2023 Total FHTC to be given - 3243, FHTC given as on 18/7/23 - 1504, HTC given as on 18/7/23 - 15, Waiting for PWD cutting sanction for laying pipe. Piravom Project Dn AE 1
18 Jul 2023 Total FHTC to be given - 3243, FHTC given as on 18/7/23 - 1504, HTC given as on 18/7/23 - 15, Waiting for PWD cutting sanction for laying pipe line fora length of 31550 m Piravom Project Dn AE 1
30 Jun 2023 Total FHTC to be given - 3243, FHTC given as on 27/6/23 - 1502, HTC given as on 27/06/23 - 15 Piravom Project Dn AE 1
27 Jun 2023 Total FHTC to be given - 3243, FHTC given as on 27/6/23 - 1502, HTC given as on 27/06/23 - 15 Piravom Project Dn AE 1
22 Jun 2023 Total FHTC to be given - 3243, FHTC given as on 20/6/23 - 1498, HTC given as on 20/06/23 - 15 Piravom Project Dn AE 1
08 Jun 2023 Total FHTC to be given - 3243, FHTC given as on 25/05/23 - 1333, HTC given as on 25/05/23 - 2 Piravom Project Dn AE 1