AMRUT - Laying of 500mm DI transmission line from Pump house at Thammanam to OHSR at Kadavanthra

Project AMRUT - Laying of 500mm DI transmission line from Pump house at Thammanam to OHSR at Kadavanthra
Project Code EKMAMRUT1117867
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Laying of 500mm DI transmission line from Pump house at Thammanam to OHSR at Kadavanthra for a length of 3496 m
Status On-going
District Ernakulam
Executing Office Kochi Project Division
AS Amount (Rs) 82700000
AS Number G.O.(Rt)1952/2021/LSGD dtd 8/10/21 & GO(Rt)No.3530/2017/LSGD 02.11.2017
TS Amount (Rs) 76500000
TS Number TS/CE/CR/KWA/46/207-18
Total Bill Submitted (Rs) 79523482
Total Bill Paid (Rs) 79523482
Population Benefitted 30985
Capacity in MLD 13.00
Actual Project Completion Date 31 Aug 2022
Coverage Kadavanthra Zone of Kochi Corporation-Dn.nos.60(part),56,57,55,54,63(part)
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-Laying 500 mm DI pipe from Thammanam to Kadavanthra-Railway crossing at Km 4/300-400 near Ponnurunni by Push through method-Pipeline Work Kochi Project Division
2 AMRUT - Laying of 500mm DI transmission line from Pump house at Thammanam to OHSR at Kadavanthra Kochi Project Division
3 AMRUT SAAP 2016-17 - Supply, Erection, Testing and commissioning of 2Nos of Centrifugal Pump sets and allied works at Thammanam Pump House Kochi Project Division
4 Consultancy works for technical services for railway crossing at Ponnurunni Kochi Project Division

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Aug 2022 Thammanam Kadavantara work :shifting of pumpset -started at thammanam pump house Kochi JNURM Projects AE-6
16 Aug 2022 Clarification sought by railway is submitted to railway division office. Pump set erection works are progressing at Thammanam P.H. Kochi Project -AEE 3
06 Aug 2022 Pump set erection work on progress. Kochi JNURM Projects AE-6
02 Aug 2022 Pump set erection work on progress. Kochi JNURM Projects AE-6
13 Jun 2022 Centage charge remitted to Railway. Kochi JNURM Projects AE-6

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/06/2018
Scheduled date of Completion of the Project 22 Feb 2019
Expected date of Completion 30/11/2022

Processing Dates

AS Date 06 Aug 2020
TS Date 28 Nov 2017

Other details

Project Officers View