| Project | Consultancy works for technical services for railway crossing at Ponnurunni |
|---|---|
| Project Code | EKMAMRUT1117867P5 |
| Type | Package |
| Main Project | AMRUT - Laying of 500mm DI transmission line from Pump house at Thammanam to OHSR at Kadavanthra |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | Consulancy job as mentioned - crossing the railway line below Vytilla bridge is pending in Thammanam - Kadavanthra pipe laying work. Permission from Railway is needed for laying the pipe line below Railway line. Railway directed to submit several details/drawings including design .The design has to be proof checked by reputed institution .Then only Railway can process and forward the file to their Head quarters. To submit the details and obtain permission consultancy help is needed. |
| Status | On-going |
| District | Ernakulam |
| Executing Office | Kochi Project Division |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 284000 |
| TS Number | TS/2021-2022/2022/2081 |
| Technical specification | |
| Contractor | M/s Southern Telecom (Mob: 8089009202) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 11/02/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 27 Mar 2022 |
| Expected date of Completion | 31/10/2022 |
| TS Date | 25 Jan 2022 |
|---|---|
| Estimate Approval | 25 Jan 2022 |
| NIT Approval | 25 Jan 2022 |
| Workorder Date | 08 Feb 2022 |
|---|---|
| NA | 11 Feb 2022 |
| Kochi JNURM Projects AE-6 |
| Date: 31/10/2022 |
Work has been completed | 100% Completed
Work completed..
| Kochi JNURM Projects AE-6 |
| Date: 29/10/2022 |
Work in progress | 98% Completed
Work completed. .