25 Aug 2022 Thammanam Kadavantara work :shifting of pumpset -started at thammanam pump house Kochi JNURM Projects AE-6
16 Aug 2022 Clarification sought by railway is submitted to railway division office. Pump set erection works are progressing at Thammanam P.H. Kochi Project -AEE 3
06 Aug 2022 Pump set erection work on progress. Kochi JNURM Projects AE-6
02 Aug 2022 Pump set erection work on progress. Kochi JNURM Projects AE-6
13 Jun 2022 Centage charge remitted to Railway. Kochi JNURM Projects AE-6
20 May 2022 Request sent to NIT, Surathkal for vetting the push through calculation. Kochi JNURM Projects AE-6
11 May 2022 The design calculation submitted to Railway is under scrtiny at Railway Division Office, Thiruvananthapuram. Kochi JNURM Projects AE-6
28 Apr 2022 Follow up with Railway Divisional Office, Thiruvananthapuram. Kochi JNURM Projects AE-6
20 Apr 2022 Follow up with Railway Divisional Office, Thiruvananthapuram. Kochi JNURM Projects AE-6
08 Apr 2022 Calculation under process at Railway Divisional Office Thiruvananthapuram. Kochi JNURM Projects AE-6