| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Aug 2022 | Thammanam Kadavantara work :shifting of pumpset -started at thammanam pump house | Kochi JNURM Projects AE-6 | |
| 16 Aug 2022 | Clarification sought by railway is submitted to railway division office. Pump set erection works are progressing at Thammanam P.H. | Kochi Project -AEE 3 | |
| 06 Aug 2022 | Pump set erection work on progress. | Kochi JNURM Projects AE-6 | |
| 02 Aug 2022 | Pump set erection work on progress. | Kochi JNURM Projects AE-6 | |
| 13 Jun 2022 | Centage charge remitted to Railway. | Kochi JNURM Projects AE-6 | |
| 20 May 2022 | Request sent to NIT, Surathkal for vetting the push through calculation. | Kochi JNURM Projects AE-6 | |
| 11 May 2022 | The design calculation submitted to Railway is under scrtiny at Railway Division Office, Thiruvananthapuram. | Kochi JNURM Projects AE-6 | |
| 28 Apr 2022 | Follow up with Railway Divisional Office, Thiruvananthapuram. | Kochi JNURM Projects AE-6 | |
| 20 Apr 2022 | Follow up with Railway Divisional Office, Thiruvananthapuram. | Kochi JNURM Projects AE-6 | |
| 08 Apr 2022 | Calculation under process at Railway Divisional Office Thiruvananthapuram. | Kochi JNURM Projects AE-6 |