13th finance commission award -Grant for kuttanad development proposal of KWA for completing the clean water transmission main of the kuttanad water supply augmentation scheme

Project 13th finance commission award -Grant for kuttanad development proposal of KWA for completing the clean water transmission main of the kuttanad water supply augmentation scheme
Project Code ALPGOK1013621
Type Main project
Funding Agency GOK
Category Completion of Ongoing Rural WSS
Type of scheme Water Supply
Scheme 2215-02-106-97
Description 13th finance commission award -Grant for kuttanad development proposal of KWA for completing the clear water transmission main of the kuttanad water supply augmentation scheme
Status Completed
District Alappuzha
Executing Office KIIFB Projects (ALP)
AS Amount (Rs) 700000000
AS Number WS/107/2013-14
TS Amount (Rs) 700000000
TS Number KWA/CE(SR)/45/2013-14
Total Bill Submitted (Rs) 568300000
Total Bill Paid (Rs) 568300000
Population Benefitted 115880
Capacity in MLD 14.00
Actual Project Completion Date 31 May 2023
Coverage Distribution network in Muttar, Veliyanad,Edathua,Thalavady, Thakazhy and Neelamperoor panchayaths .Transmission lines to veliyanad, Neelamperoor, veeyapuram,Ramankary, Chambakkulam, Pulinkunnu and Kavalam panchayaths.4.5LL OHSR at Thakazhy panchayath.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Package- III-13th finance Commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system 1 and construction of 4.5 LL capacity OH tank at Thakazhy) Alappuzha Project Dn
2 Package -II-Transmission system II-13th finance commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm(Neerettupuram to Mampuzhakary and Pallikkuttumma to Kavalam) Alappuzha Project Dn
3 Package-I-Transmission system I-13th Finance Commission - Aug: of Kuttanad WSS-Supply,laying,jointing,testing and commissioning of HDPE pipe ranging from 200mm to 500mm for system I(Kidangara to Neelamperoor and Edathua to Veeyapuram) Alappuzha Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Dec 2023 Package 1,2 & 3 completed. Alappuzha KIIFB - AE 1
30 May 2022 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. The MS fabrication work at Muttar panchayath 12 nos. gap completed.90 mm HDPE pipe laying at Veliyanad panchayath 800m completed. Contractor not carrying out balance works. Notice issued to contractor to complete the balance work otherwise will be arranged at his risk and cost. Soil investigation works for railway crossing arranged through NIT Kozhikkode. Alappuzha KIIFB - AE 1
08 Jan 2022 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. MS fabrication works in Muttar panchayat is in progress. Soil investigation works for railway crossing arranged Alappuzha KIIFB - AE 1
08 Jan 2022 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. The MS fabrication works in Muttar panchath is in progress. Soil investigation works for railway crossing arranged and report to railway can be submitted by 31/12/2021. Alappuzha KIIFB - AE 1
20 Dec 2021 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. Pipe laying works, gap closing and interconnection works could not be proceeded due to rise in water table during heavy rains. Work resumed on 17/12/2021. Soil investigation works for railway crossing arranged and report to railway can be submitted by 31/12/2021. Alappuzha KIIFB - AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/07/2014
Scheduled date of Completion of the Project 02 Feb 2016
Expected date of Completion 31/01/2022

Processing Dates

AS Date 28 Dec 2013
TS Date 01 Jan 2014

Other details

Project Officers View