Package- III-13th finance Commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system 1 and construction of 4.5 LL capacity OH tank at Thakazhy)

Project Package- III-13th finance Commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system 1 and construction of 4.5 LL capacity OH tank at Thakazhy)
Project Code ALPGOK1013621P3
Type Package
Main Project 13th finance commission award -Grant for kuttanad development proposal of KWA for completing the clean water transmission main of the kuttanad water supply augmentation scheme
Funding Agency GOK
Category Completion of Ongoing Rural WSS
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Package III-13th finance Commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system 1 and construction of 4.5 LL capacity OH tank at Thakazhy
Status Completed
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 700000000
TS Number KWA/CE(SR)/PHTVL/5150/2013
Technical specification Laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system ) and construction of 4.5 LL capacity OH tank at Thakazhy
Contractor M/s Process Construction and Technical Services Pvt. Ltd (Mob: 9820238209)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Sep 2021 Pending 10 Sep 2021 Road Cut Related Risk 1) PWD Sanction not received yet for Muttar Central road. 2) Even though we have remitted the amount demanded by PWD, permission from KRFB required for AT road. 3) Even though we have remitted the amount demanded by PWD, permission from KSTP required for Kidangara - Kannadi road and Kunnamkari - kumarmkari road road and AC road. No comments added. Action Taken
10 Oct 2020 Pending Pending Contract Related Risks Railway crossing is required at Thakazhi (Ch.74/100-74/200, Between Ambalapuzha and Thakazhy Stations) for the successful completion of this Package. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/02/2015
Scheduled date of Completion as per agreement 02 Feb 2016
Expected date of Completion 31/03/2022

Processing Dates

TS Date 01 Jan 2014
Estimate Approval 22 Jul 2014
NIT Approval 23 Jul 2014
Tender Closing 18 Aug 2014
Technichal Pre-Qualification 23 Aug 2014
Price bid opening 29 Aug 2014

Approval Dates

Workorder Date 15 Jan 2015
NA 03 Feb 2015

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha KIIFB - AE 1
Date: 29/09/2023

Work has been completed | 100% Completed

Work completed..

Alappuzha KIIFB - AE 1
Date: 27/09/2023

Work in progress | 96% Completed

Gap work completed.