Package- III-13th finance Commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system 1 and construction of 4.5 LL capacity OH tank at Thakazhy)
Project |
Package- III-13th finance Commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system 1 and construction of 4.5 LL capacity OH tank at Thakazhy) |
Project Code |
ALPGOK1013621P3 |
Type |
Package |
Main Project |
13th finance commission award -Grant for kuttanad development proposal of KWA for completing the clean water transmission main of the kuttanad water supply augmentation scheme
|
Funding Agency |
GOK |
Category |
Completion of Ongoing Rural WSS |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Package III-13th finance Commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system 1 and construction of 4.5 LL capacity OH tank at Thakazhy |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Alappuzha Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
700000000 |
TS Number |
KWA/CE(SR)/PHTVL/5150/2013 |
Technical specification |
Laying,testing and commissioning of transmission pipe using various size of HDPE & DI (pipe for distribution system ) and construction of 4.5 LL capacity OH tank at Thakazhy |
Contractor |
M/s Process Construction and Technical Services Pvt. Ltd (Mob: 9820238209) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
01 Sep 2021 |
Pending |
10 Sep 2021 |
Road Cut Related Risk |
1) PWD Sanction not received yet for Muttar Central road.
2) Even though we have remitted the amount demanded by PWD, permission from KRFB required for AT road.
3) Even though we have remitted the amount demanded by PWD, permission from KSTP required for Kidangara - Kannadi road and Kunnamkari - kumarmkari road road and AC road. |
No comments added. |
Action Taken |
10 Oct 2020 |
Pending |
Pending |
Contract Related Risks |
Railway crossing is required at Thakazhi (Ch.74/100-74/200, Between Ambalapuzha and Thakazhy Stations) for the successful completion of this Package. |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
03/02/2015 |
Scheduled date of Completion as per agreement |
02 Feb 2016 |
Expected date of Completion |
31/03/2022 |
Processing Dates
TS Date |
01 Jan 2014 |
Estimate Approval |
22 Jul 2014 |
NIT Approval |
23 Jul 2014 |
Tender Closing |
18 Aug 2014 |
Technichal Pre-Qualification |
23 Aug 2014 |
Price bid opening |
29 Aug 2014 |
Approval Dates
Workorder Date |
15 Jan 2015 |
NA |
03 Feb 2015 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 1 |
Date: 29/09/2023 |
Work has been completed | 100% Completed
Work completed..
Alappuzha KIIFB - AE 1 |
Date: 27/09/2023 |
Work in progress | 96% Completed
Gap work completed.