Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Dec 2023 Package 1,2 & 3 completed. Alappuzha KIIFB - AE 1
30 May 2022 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. The MS fabrication work at Muttar panchayath 12 nos. gap completed.90 mm HDPE pipe laying at Veliyanad panchayath 800m completed. Contractor not carrying out balance works. Notice issued to contractor to complete the balance work otherwise will be arranged at his risk and cost. Soil investigation works for railway crossing arranged through NIT Kozhikkode. Alappuzha KIIFB - AE 1
08 Jan 2022 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. MS fabrication works in Muttar panchayat is in progress. Soil investigation works for railway crossing arranged Alappuzha KIIFB - AE 1
08 Jan 2022 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. The MS fabrication works in Muttar panchath is in progress. Soil investigation works for railway crossing arranged and report to railway can be submitted by 31/12/2021. Alappuzha KIIFB - AE 1
20 Dec 2021 Package 1&2 completed. Under package 3, 36.8 km pipe line out of 46 km distribution mains to 6 panchayats completed. Pipe laying works, gap closing and interconnection works could not be proceeded due to rise in water table during heavy rains. Work resumed on 17/12/2021. Soil investigation works for railway crossing arranged and report to railway can be submitted by 31/12/2021. Alappuzha KIIFB - AE 1
26 Aug 2021 Package 1&2 completed. The laying of HDPE pipes/ inter connection works/ Gap closing works as a part of Package -3 in PWD roads are pending due to Monsoon ban by PWD. Alappuzha KIIFB - AE 1
23 Jun 2021 Package 1&2 completed. The laying of HDPE pipes/ inter connection works/ Gap closing works as a part of Package -3 in PWD roads are pending due to Monsoon ban by PWD. Alappuzha Project Dn AE 3
23 Jun 2021 Package 1&2 completed. The laying of HDPE pipes/ inter connection works/ Gap closing works as a part of Package -3 in PWDs are pending due to Monsoon ban. Alappuzha Project Dn AE 3
15 Jun 2021 Package 1 and 2 completed. For package 3 pipe laying works Road cutting permission applied through ROW portal for different PWD roads in Kuttanad taluk and PWD demanded the road restoration charge. Road restoration charge remitted to PWD Alappuzha Division on 5-3-2021 , the documents submitted to the PWD roads subdivision Kuttanad and the agreement is not yet executed. There is a road cutting ban on PWD roads during election time up to 2-5-2021 and after that the inter connection works in panchayath roads started and the works stopped due to high water table in Kuttanad. Waiting for the permission of PWD for balance pipe laying works. Alappuzha Project Dn AE 3
02 Jun 2021 Package 1 and 2 completed. For package 3 pipe laying works Road cutting permission applied through ROW portal for different PWD roads in Kuttanad taluk and PWD demanded the road restoration charge. Road restoration charge remitted to PWD Alappuzha Division on 5-3-2021 , the documents submitted to the PWD roads subdivision Kuttanad and the agreement is not yet executed. There is a road cutting ban on PWD roads during election time up to 2-5-2021 and after that the inter connection works in panchayath roads started and the works stopped due to high water table in Kuttanad. Waiting for the permission of PWD for balance pipe laying works. Alappuzha Project Dn AE 3