Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Package -II-Transmission system II-13th finance commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm(Neerettupuram to Mampuzhakary and Pallikkuttumma to Kavalam)

Project Package -II-Transmission system II-13th finance commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm(Neerettupuram to Mampuzhakary and Pallikkuttumma to Kavalam)
Project Code ALPGOK1013621P2
Type Package
Main Project 13th finance commission award -Grant for kuttanad development proposal of KWA for completing the clean water transmission main of the kuttanad water supply augmentation scheme
Funding Agency GOK
Category Completion of Ongoing Rural WSS
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Package-II-Transmission system II-13th finance commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm(Neerettupuram to Mampuzhakary and Pallikkuttumma to Kavalam)
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 700000000
TS Number KWA/CE(SR)/PHTVL/5150/2013
Technical specification supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/09/2014
Scheduled date of Completion as per agreement 04 Sep 2015
Expected date of Completion 04/09/2015

Processing Dates

TS Date 01 Jan 2014
Estimate Approval 27 Mar 2014
NIT Approval 28 Mar 2014
Tender Closing 22 Apr 2014
Technichal Pre-Qualification 25 Apr 2014
Price bid opening 28 May 2014

Approval Dates

Workorder Date 19 Aug 2014
NA 05 Sep 2014

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha KIIFB - AE 1
Date: 11/07/2022

Work has been completed | 100% Completed

completed.

Alappuzha KIIFB - AE 1
Date: 10/07/2022

Work has been completed | 100% Completed

completed.