Package -II-Transmission system II-13th finance commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm(Neerettupuram to Mampuzhakary and Pallikkuttumma to Kavalam)
Project |
Package -II-Transmission system II-13th finance commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm(Neerettupuram to Mampuzhakary and Pallikkuttumma to Kavalam) |
Project Code |
ALPGOK1013621P2 |
Type |
Package |
Main Project |
13th finance commission award -Grant for kuttanad development proposal of KWA for completing the clean water transmission main of the kuttanad water supply augmentation scheme
|
Funding Agency |
GOK |
Category |
Completion of Ongoing Rural WSS |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Package-II-Transmission system II-13th finance commission-Aug of kuttanad WSS supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm(Neerettupuram to Mampuzhakary and Pallikkuttumma to Kavalam) |
Status |
On-going |
District |
Alappuzha |
Executing Office |
Alappuzha Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
700000000 |
TS Number |
KWA/CE(SR)/PHTVL/5150/2013 |
Technical specification |
supply ,laying,testing and commissioning of transmission pipe using various size of HDPE pipe ranging from 200mm to 800mm |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
05/09/2014 |
Scheduled date of Completion as per agreement |
04 Sep 2015 |
Expected date of Completion |
04/09/2015 |
Processing Dates
TS Date |
01 Jan 2014 |
Estimate Approval |
27 Mar 2014 |
NIT Approval |
28 Mar 2014 |
Tender Closing |
22 Apr 2014 |
Technichal Pre-Qualification |
25 Apr 2014 |
Price bid opening |
28 May 2014 |
Approval Dates
Workorder Date |
19 Aug 2014 |
NA |
05 Sep 2014 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 1 |
Date: 11/07/2022 |
Work has been completed | 100% Completed
completed.
Alappuzha KIIFB - AE 1 |
Date: 10/07/2022 |
Work has been completed | 100% Completed
completed.