Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira

Project Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira
Project Code KLMGOK0117465P1
Type Package
Main Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Description Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira AS Amount Rs.2350000000(235Crore)
Status On-going
District Kollam
Executing Office Kollam Project Dn
TS Amount (Rs) 1455200000
TS Number KWA/CE(SR)/18-2016-17 dtd 23/01/2017
Technical specification Supplying, laying, Commissioning and maintaining 1219mm M.S pipe 12.5mm thick for a length of 16035m and 10mm thick for a length of 12095m for raw water Pumping Main from Intake to TP at Vasoorichira

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 02/06/2018
Scheduled date of Completion as per agreement 01 Jun 2020
Expected date of Completion 31/01/2021

Processing Dates

TS Date 23 Jan 2017
Estimate Approval 23 Jan 2017
Tender Closing 25 Jan 2018
Technichal Pre-Qualification 27 Jan 2018
Price bid opening 27 Jan 2018

Approval Dates

CE Approval 11 May 2018
Head Office Approval 11 May 2018
Board Approval 11 May 2018
Final Approval 11 May 2018
Workorder Date 18 May 2018
Agreement Date 02 Jun 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 03/06/2021

Work in progress | 94% Completed

WORK TEMPORARILY STOPPED DUE TO CIVID + ve REPORTED FOR LABOURS AND SUPERVISORS, NON AVAILABILITY OF OXYGEN CYLINDER. Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.84 meters completed. Out of 28130 meters of pipe-laying work 26706.02 meters of work completed. TOTAL HYDROTEST 23701.55 METER COMPLETED. Remaining length testing is on progress..

Kollam Project Dn EE
Date: 02/06/2021

Work in progress | 94% Completed

WORK TEMPORARILY STOPPED DUE TO CIVID + ve REPORTED FOR LABOURS AND SUPERVISORS, NON AVAILABILITY OF OXYGEN CYLINDER. Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.84 meters completed. Out of 28130 meters of pipe-laying work 26706.02 meters of work completed. TOTAL HYDROTEST 23701.55 METER COMPLETED. Remaining length testing is on progress. .