| Project | Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira |
|---|---|
| Project Code | KLMGOK0117465P1 |
| Type | Package |
| Main Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503) |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira AS Amount Rs.2350000000(235Crore) |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| TS Amount (Rs) | 1455200000 |
| TS Number | KWA/CE(SR)/18-2016-17 dtd 23/01/2017 |
| Technical specification | Supplying, laying, Commissioning and maintaining 1219mm M.S pipe 12.5mm thick for a length of 16035m and 10mm thick for a length of 12095m for raw water Pumping Main from Intake to TP at Vasoorichira |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 02/06/2018 |
|---|---|
| Scheduled date of Completion as per agreement | 01 Jun 2020 |
| Expected date of Completion | 31/01/2021 |
| TS Date | 23 Jan 2017 |
|---|---|
| Estimate Approval | 23 Jan 2017 |
| Tender Closing | 25 Jan 2018 |
| Technichal Pre-Qualification | 27 Jan 2018 |
| Price bid opening | 27 Jan 2018 |
| CE Approval | 11 May 2018 |
|---|---|
| Head Office Approval | 11 May 2018 |
| Board Approval | 11 May 2018 |
| Final Approval | 11 May 2018 |
| Workorder Date | 18 May 2018 |
| Agreement Date | 02 Jun 2018 |
| Kollam Project Dn EE |
| Date: 03/06/2021 |
Work in progress | 94% Completed
WORK TEMPORARILY STOPPED DUE TO CIVID + ve REPORTED FOR LABOURS AND SUPERVISORS, NON AVAILABILITY OF OXYGEN CYLINDER. Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.84 meters completed. Out of 28130 meters of pipe-laying work 26706.02 meters of work completed. TOTAL HYDROTEST 23701.55 METER COMPLETED. Remaining length testing is on progress..
| Kollam Project Dn EE |
| Date: 02/06/2021 |
Work in progress | 94% Completed
WORK TEMPORARILY STOPPED DUE TO CIVID + ve REPORTED FOR LABOURS AND SUPERVISORS, NON AVAILABILITY OF OXYGEN CYLINDER. Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.84 meters completed. Out of 28130 meters of pipe-laying work 26706.02 meters of work completed. TOTAL HYDROTEST 23701.55 METER COMPLETED. Remaining length testing is on progress. .