AMRUT 2.0 - WSS to Thripunithura municipality - Providing FHTC's by augmenting or retrofitting the existing water supply scheme and laying new rider line

Project AMRUT 2.0 - WSS to Thripunithura municipality - Providing FHTC's by augmenting or retrofitting the existing water supply scheme and laying new rider line
Project Code EKMAMRUT112213363
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT 2.0 - WSS to Thripunithura municipality - Providing FHTC's by augmenting or retrofitting the existing water supply scheme and laying new rider line
Status On-going
District Ernakulam
Executing Office Kochi WS Dn
AS Amount (Rs) 122899999
AS Number GO(Rt)No.2906/2022/LSGD
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 5804109
Total Bill Paid (Rs) 5871538
Population Benefitted 11350
Capacity in MLD 10.00
Actual Project Completion Date 31 Mar 2024
Coverage Thripunithura municipality

Packages

No. Project Name Location View
1 AMRUT-2.0-AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-4,5,6,11,12,13 and 14 )- Package II-Pipeline Work-Pipeline Work Trippunnithura WS Sn 1
2 AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-15,16,22,23,24 and 25)- Package I-Pipeline Work Trippunnithura WS Sn 2
3 AMRUT-2.0-WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Laying 200mm DI (K9) pumping main from Karingachira PH to Tracco for a length of 4550m. and allied works )- Package III-Pipeline Work Trippunnithura WS Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Mar 2024 Package I- 84% completedPackage-II-85% CompletedPackage II-Submitted to Govt. For Tender excess approval Kochi WS Dn EE
14 Feb 2024 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Thripunithura WS Sn - AE 1
17 Dec 2023 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Kochi WS Dn EE
11 Dec 2023 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Kochi WS Dn EE
05 Dec 2023 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Thripunithura WS Sn - AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/06/2023
Scheduled date of Completion of the Project 30 Sep 2033
Expected date of Completion 31/03/2025

Processing Dates

AS Date 24 Nov 2022

Other details

Project Officers View