AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-15,16,22,23,24 and 25)- Package I-Pipeline Work

Project AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-15,16,22,23,24 and 25)- Package I-Pipeline Work
Project Code EKMAMRUT112213363P1
Type Package
Main Project AMRUT 2.0 - WSS to Thripunithura municipality - Providing FHTC's by augmenting or retrofitting the existing water supply scheme and laying new rider line
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-15,16,22,23,24 and 25)- Package I-Pipeline Work
Status On-going
District Ernakulam
Executing Office Trippunnithura WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 33540000
TS Number WRD/KWA-CE(CR)/EST_TS/13752/2022_26_1_1
Technical specification Providing FHTC's by augmenting or retrofitting
Contractor M/S Andhyodaya (Mob: 9388607010)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/06/2023
Scheduled date of Completion as per agreement 31 Mar 2024
Expected date of Completion 31/03/2024

Processing Dates

TS Date 27 Feb 2023
Estimate Approval 27 Feb 2023
NIT Approval 29 Mar 2023
Tender Closing 10 Apr 2023
Technichal Pre-Qualification 10 Apr 2023
Price bid opening 11 Apr 2023

Approval Dates

Workorder Date 23 May 2023
NA 05 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thripunithura WS Sn - AE 1
Date: 10/05/2024

Work in progress | 89% Completed

On going.

Thripunithura WS Sn - AE 1
Date: 06/05/2024

Work in progress | 89% Completed

On going.