AMRUT-2.0-AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-4,5,6,11,12,13 and 14 )- Package II-Pipeline Work-Pipeline Work

Project AMRUT-2.0-AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-4,5,6,11,12,13 and 14 )- Package II-Pipeline Work-Pipeline Work
Project Code EKMAMRUT112213363P2
Type Package
Main Project AMRUT 2.0 - WSS to Thripunithura municipality - Providing FHTC's by augmenting or retrofitting the existing water supply scheme and laying new rider line
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2.0-AMRUT-2.0-AMRUT 2.0 -WSS to Tripunithura Municipality - Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line-(Thiruvankulam Zone -Ward Nos-4,5,6,11,12,13 and 14 )- Package II-Pipeline Work-Pipeline Work
Status On-going
District Ernakulam
Executing Office Trippunnithura WS Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 122899999
TS Number WRD/KWA-CE(CR)/EST_TS/13627/2022_26_1_1
Technical specification Providing FHTC, by augmenting or retrofitting the existing Water Supply Scheme and laying new rider line
Contractor K K Ramesan (Mob: 9447192057)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/07/2023
Scheduled date of Completion as per agreement 02 Nov 2023
Expected date of Completion 31/03/2024

Processing Dates

TS Date 24 Apr 2023
Estimate Approval 24 Apr 2023
NIT Approval 09 May 2023
Tender Closing 22 May 2023
Technichal Pre-Qualification 22 May 2023
Price bid opening 23 May 2023

Approval Dates

Workorder Date 05 Jun 2023
NA 03 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thripunithura WS Sn - AE 1
Date: 10/05/2024

Work in progress | 92% Completed

On going.

Thripunithura WS Sn - AE 1
Date: 07/05/2024

Work in progress | 92% Completed

On going.