Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Mar 2024 Package I- 84% completedPackage-II-85% CompletedPackage II-Submitted to Govt. For Tender excess approval Kochi WS Dn EE
14 Feb 2024 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Thripunithura WS Sn - AE 1
17 Dec 2023 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Kochi WS Dn EE
11 Dec 2023 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Kochi WS Dn EE
05 Dec 2023 Package 1 & 2 - work in progress, Package 3 - tendered and submitted to Govt. for excess sanction Thripunithura WS Sn - AE 1
12 Oct 2023 Package 1 &2 - work in progress , Package 3 - Retendered Thripunithura WS Sn - AE 1
29 Sep 2023 Package 1 &2 - work in progress , Package 3 - Retendered Thripunithura WS Sn - AE 1
18 Sep 2023 Package 1 &2 - work in progress , Package 3 - Retendered Trippunithura WS Sub Dn - AEE
15 Sep 2023 Package 1 &2 - work in progress , Package 3 - Retendered Thripunithura WS Sn - AE 1
11 Sep 2023 Package 1 &2 - work in progress , Package 3 - Retendered with due date 13.09.2023 Thripunithura WS Sn - AE 1