| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Dec 2022 | Bill submitted | Plamoodu Sewerage Project Sn AE | |
| 26 Sep 2022 | All work completed | Plamoodu Sewerage Project Sn AE | |
| 21 Sep 2022 | Removal of excess earth is in progress | Plamoodu Sewerage Project Sn AE | |
| 19 Sep 2022 | Earth filling work in progress | Plamoodu Sewerage Project Sn AE | |
| 12 Sep 2022 | 682 m pipe laid and 41 MH casted | Plamoodu Sewerage Project Sn AE | |
| 06 Sep 2022 | Earth filling work is in progress. | Plamoodu Sewerage Project Sn AE | |
| 31 Aug 2022 | Work temporarily halted due to rain | Plamoodu Sewerage Project Sn AE | |
| 26 Aug 2022 | 680 m pipe laid and 40 MH casted and 1 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 25 Aug 2022 | 2 days no work due to rain | Pattoor Sewerage Sub Dn AEE | |
| 19 Aug 2022 | Manhole construction work is in progress | Plamoodu Sewerage Project Sn AE |