State Plan-2020-21-TSS - Providing and laying 300mm dia main and 200mm SW branch sewer line towards Sreekrishna Nagar infront of Jagathy School in Jagathy Kochar Road

Project State Plan-2020-21-TSS - Providing and laying 300mm dia main and 200mm SW branch sewer line towards Sreekrishna Nagar infront of Jagathy School in Jagathy Kochar Road
Project Code TVMGOK10204314
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description TSS - Providing and laying 300mm dia main and 200mm SW branch sewer line towards Sreekrishna Nagar infront of Jagathy School in Jagathy Kochar Road
Status Completed
District Thiruvananthapuram
Executing Office Plamoodu project Sn
AS Amount (Rs) 11300000
AS Number KWA/JB/P4/9/2020-21 (VI)
TS Amount (Rs) 10510000
TS Number 13154/2021-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 200
Capacity in MLD 0.25
Actual Project Completion Date 30 Sep 2022
Coverage Sreekrishna Nagar infront of Jagathy School in Jagathy Kochar Road
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan-2020-21-TSS - Providing and laying 300mm dia main and 200mm SW branch sewer line towards Sreekrishna Nagar infront of Jagathy School in Jagathy Kochar Road Plamoodu project Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Dec 2022 Bill submitted Plamoodu Sewerage Project Sn AE
26 Sep 2022 All work completed Plamoodu Sewerage Project Sn AE
21 Sep 2022 Removal of excess earth is in progress Plamoodu Sewerage Project Sn AE
19 Sep 2022 Earth filling work in progress Plamoodu Sewerage Project Sn AE
12 Sep 2022 682 m pipe laid and 41 MH casted Plamoodu Sewerage Project Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/02/2022
Scheduled date of Completion of the Project 13 Aug 2022
Expected date of Completion 30/09/2022

Processing Dates

AS Date 08 Oct 2020
TS Date 16 Nov 2021

Other details

Project Officers View