| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Mar 2022 | pipe line work completed up to 175 meters . 10MH completed. | Plamoodu Sewerage Project Sn AE | |
| 26 Feb 2022 | pipe line work completed up to 155 meters . 9 MH in branch 1 completed. | Plamoodu Sewerage Project Sn AE | |
| 25 Feb 2022 | pipe line work completed up to 155 meters . 9 MH in branch 1 completed. | Plamoodu Sewerage Project Sn AE | |
| 23 Feb 2022 | pipe line work completed up to 140 meters . 9 MH in branch 1 completed. | Plamoodu Sewerage Project Sn AE | |
| 23 Feb 2022 | pipe line work completed up to 120 meters . 9 MH in branch 1 completed. | Plamoodu Sewerage Project Sn AE | |
| 22 Feb 2022 | pipe line work completed up to 120 meters . 9 MH in branch 1 completed. | Plamoodu Sewerage Project Sn AE | |
| 21 Feb 2022 | pipe line work completed up to 120 meters . 9 MH in branch 1 completed. | Plamoodu Sewerage Project Sn AE | |
| 19 Feb 2022 | pipe line work completed up to 85 meters . MH10 & 9 concreted and MH No.8 under progress in branch 1. | Plamoodu Sewerage Project Sn AE | |
| 18 Feb 2022 | pipe line work completed up to 85 meters . MH10 & 9 concreted and MH No.8 under progress in branch 1. | Plamoodu Sewerage Project Sn AE | |
| 15 Feb 2022 | pipe line work completed up to 28 meters | Pattoor Sewerage Sub Dn AEE |