| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Feb 2021 | interconnection work in progress | Adoor Project Dn EE | |
| 03 Feb 2021 | Interconnection and gap closing works in progress | Adoor Project Dn EE | |
| 27 Jan 2021 | 90 km laid | Adoor Project Dn EE | |
| 25 Jan 2021 | 88 km pipe line laid | Adoor Project Dn EE | |
| 21 Dec 2020 | 82 KM PIPE LINE LAID | Adoor Project Dn EE | |
| 16 Dec 2020 | 80 km pipe line laid | Adoor Project Dn EE | |
| 23 Nov 2020 | LAYING PIPE LINES IN PWD ROAD STARTED | Adoor Project Dn EE | |
| 23 Nov 2020 | 75 km laid out of 118 km | Adoor Project Dn EE | |
| 07 Oct 2020 | 62 KM PIPE LINE LAID OUT OF 118 KM | Adoor Project Dn EE | |
| 07 Oct 2020 | ALL SIZES OF DI PIPES SUPPLIED EXCEPT 350 | Adoor Project Dn EE |