| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Aug 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 05 Aug 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 03 Aug 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 02 Aug 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 30 Jul 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 29 Jul 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 28 Jul 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 26 Jul 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 26 Jul 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn AE3 | |
| 23 Jul 2021 | Package 1-pipe laying work Panachimoodu jn & road restoration work in progress Package 2 - MS fabrication work in Parumala bridge in progress Package 3- Not started | Adoor Project Dn EE |