Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Jun 2021 Interconnection works at niranam started Adoor Project Dn EE
11 Jun 2021 Pipe laying in Parumala - Illimala in progress Adoor Project Dn EE
03 Jun 2021 110 km completed Adoor Project Dn EE
02 Jun 2021 110 km completed Adoor Project Dn EE
30 May 2021 Mavelikkara- Thiruvalla road crossing in progress Adoor Project Dn EE
04 May 2021 105 km pipeline completed Adoor Project Dn EE
14 Apr 2021 98 KM COMPLETED Adoor Project Dn EE
31 Mar 2021 Charging in Panachimudu junction in progress Adoor Project Dn EE
26 Mar 2021 Pipe laying in progress Adoor Project Dn EE
24 Mar 2021 Vadkkumbhagam area CHARGED Adoor Project Dn EE