Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Jun 2025 | pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain | Mattannur WS Sn | |
18 Jun 2025 | pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain | Mattannur WS Sn | |
16 Jun 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
14 May 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
30 Apr 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
16 Apr 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
01 Apr 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
16 Mar 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
07 Mar 2025 | pipe laying work is going on - 44 Km completed | Mattannur WS Sn | |
25 Feb 2025 | pipe laying work is going on - 44 Km completed | Mattannur WS Sn |