| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Dec 2024 | pipe laying work is going on | Mattannur WS Sn | |
| 12 Dec 2024 | pipe laying work is going on | Mattannur WS Sn | |
| 03 Dec 2024 | pipe laying work is going on | Mattannur WS Sn | |
| 25 Nov 2024 | 21 km pipe laying work completed | Mattannur WS Sn | |
| 18 Nov 2024 | Pipe laying work in progresss | Mattannur WS Sn | |
| 11 Nov 2024 | FHTC - 363 Nos, HTC - 105Nos, Pipe laying work in progresss | Mattannur WS Sn | |
| 04 Nov 2024 | FHTC - 363 Nos, HTC - 105Nos | Mattannur WS Sn | |
| 28 Oct 2024 | FHTC - 315 Nos, HTC - 105Nos | Mattannur WS Sn | |
| 21 Oct 2024 | FHTC - 220 Nos, HTC - 105Nos | Mattannur WS Sn | |
| 16 Oct 2024 | FHTC - 218 Nos, HTC - 105Nos | Mattannur WS Sn |