| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Aug 2025 | pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain | Mattannur WS Sn | |
| 31 Jul 2025 | pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain | Mattannur WS Sn | |
| 21 Jul 2025 | pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain | Mattannur WS Sn | |
| 30 Jun 2025 | pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain | Mattannur WS Sn | |
| 18 Jun 2025 | pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain | Mattannur WS Sn | |
| 16 Jun 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
| 14 May 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
| 30 Apr 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
| 16 Apr 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn | |
| 01 Apr 2025 | pipe laying work is going on - 52 Km completed | Mattannur WS Sn |