Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation-WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation-WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work
Project Code KNRJJM102316026
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation-WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work
Status On-going
District Kannur
Executing Office Mattannur PH Sn
AS Amount (Rs) 151700000
AS Number G.O.(Rt)No.897/2023/WRD Dated,Thiruvananthapuram, 26-10-2023
TS Amount (Rs) 139000000
TS Number 23185/2023-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 26 Nov 2024
Coverage

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation-WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work Mattannur PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Jun 2025 pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain Mattannur WS Sn
18 Jun 2025 pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain Mattannur WS Sn
16 Jun 2025 pipe laying work is going on - 52 Km completed Mattannur WS Sn
14 May 2025 pipe laying work is going on - 52 Km completed Mattannur WS Sn
30 Apr 2025 pipe laying work is going on - 52 Km completed Mattannur WS Sn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/07/2024
Scheduled date of Completion of the Project 26 Nov 2024
Expected date of Completion 31/01/2025

Processing Dates

AS Date 26 Oct 2023
TS Date 01 Jan 2024

Other details

Project Officers View