Status Date Overall Project Status Project Officer Contact
18 Nov 2020 Details updated in Package ... work started on 22.09.2020 and well in progress ... 17% of the work completed. Laying of 200 mm Pumping main work 50% completed and in progress ... For OHSR works upto Plinth beam bottom completed Kollam Project HD
12 Sep 2020 Design of 4LL OHSR approved from wascon, The contractor started Ground levelling work on 09.09.2020 Kollam Project HD
16 Aug 2020 Work was not started. Kollam Project HD