| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Nov 2020 | Details updated in Package ... work started on 22.09.2020 and well in progress ... 17% of the work completed. Laying of 200 mm Pumping main work 50% completed and in progress ... For OHSR works upto Plinth beam bottom completed | Kollam Project HD | |
| 12 Sep 2020 | Design of 4LL OHSR approved from wascon, The contractor started Ground levelling work on 09.09.2020 | Kollam Project HD | |
| 16 Aug 2020 | Work was not started. | Kollam Project HD |