Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Mar 2021 For pipe laying permission is not granted along concrete cutting near cherkulam Masjid road.for ohsr shuttering works started for 3 rs brace Kollam Project HD
20 Mar 2021 pillar rising works in progress.. Kollam Project HD
19 Mar 2021 Works upto 2 Nd brace beam completed and now pillar rising work in progress... Kollam Project HD
17 Mar 2021 Works upto 2 Nd brace beam completed and now pillar rising work in progress...For laying of pumpmain is interrupted near cherkulam Juma Masjid due to public protest for not to cut open cc road Kollam Project HD
08 Mar 2021 Works upto second brace beam completed and RCC work for second brace beam is proposed on 9.3.2021...for laying of pumping main works 93 percent completed.. Kollam Project HD
16 Feb 2021 works upto first brace beam completed and work in progress for pillar RCC above first brace beam. laying of pumping main in progress Kollam Project HD
31 Jan 2021 Work for first brace beam shuttering and reinforcement work in progress.Pumping main MS welding work in progress Kollam Project HD
31 Dec 2020 Work of pumping main in progress...hydrotesting in progress....RCC WORK upto bottom level of first brace beam in pogress Kollam Project HD
10 Dec 2020 work of pumping main laying in progress 70% completed and in progress.. Plinth beam reinforcement work and shuttering works in progress. Kollam Project HD
22 Nov 2020 Details updated in Package ... work started on 22.09.2020 and well in progress ... 17% of the work completed. Laying of 200 mm Pumping main work 52% completed and in progress ... For OHSR works upto Plinth beam bottom completed... other completed works in the above scheme 1. Distribution of zone-II - Pipe details (200, 300 & 350mm DI and 90mm to 160mmPVC - 25.41 km )ie. DI-8270m PVC-17140m - work completed on 14.09.2015 2. Distribution of zone II A -( 200, 250 & 300mm DI & 90 to 200mm PVC pipe)300mmDI-2560m,250mmDI-4414m,200mmDI-1366m PVC-11620m - work completed on 30.9.2015 3. Transmission main from Bharatheepuram to Thottamukku sump DI K9 250mm Laying - work completed on 10.10.2018 Ongoing works- 1. construction of 3.4LL sump cum pumphouse at Thottumukku - work in progress under state plan 2. Distribution for zone III - in progress - 55% completed- work in progress under state plan Kollam Project HD