| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Mar 2021 | For pipe laying permission is not granted along concrete cutting near cherkulam Masjid road.for ohsr shuttering works started for 3 rs brace | Kollam Project HD | |
| 20 Mar 2021 | pillar rising works in progress.. | Kollam Project HD | |
| 19 Mar 2021 | Works upto 2 Nd brace beam completed and now pillar rising work in progress... | Kollam Project HD | |
| 17 Mar 2021 | Works upto 2 Nd brace beam completed and now pillar rising work in progress...For laying of pumpmain is interrupted near cherkulam Juma Masjid due to public protest for not to cut open cc road | Kollam Project HD | |
| 08 Mar 2021 | Works upto second brace beam completed and RCC work for second brace beam is proposed on 9.3.2021...for laying of pumping main works 93 percent completed.. | Kollam Project HD | |
| 16 Feb 2021 | works upto first brace beam completed and work in progress for pillar RCC above first brace beam. laying of pumping main in progress | Kollam Project HD | |
| 31 Jan 2021 | Work for first brace beam shuttering and reinforcement work in progress.Pumping main MS welding work in progress | Kollam Project HD | |
| 31 Dec 2020 | Work of pumping main in progress...hydrotesting in progress....RCC WORK upto bottom level of first brace beam in pogress | Kollam Project HD | |
| 10 Dec 2020 | work of pumping main laying in progress 70% completed and in progress.. Plinth beam reinforcement work and shuttering works in progress. | Kollam Project HD | |
| 22 Nov 2020 | Details updated in Package ... work started on 22.09.2020 and well in progress ... 17% of the work completed. Laying of 200 mm Pumping main work 52% completed and in progress ... For OHSR works upto Plinth beam bottom completed... other completed works in the above scheme 1. Distribution of zone-II - Pipe details (200, 300 & 350mm DI and 90mm to 160mmPVC - 25.41 km )ie. DI-8270m PVC-17140m - work completed on 14.09.2015 2. Distribution of zone II A -( 200, 250 & 300mm DI & 90 to 200mm PVC pipe)300mmDI-2560m,250mmDI-4414m,200mmDI-1366m PVC-11620m - work completed on 30.9.2015 3. Transmission main from Bharatheepuram to Thottamukku sump DI K9 250mm Laying - work completed on 10.10.2018 Ongoing works- 1. construction of 3.4LL sump cum pumphouse at Thottumukku - work in progress under state plan 2. Distribution for zone III - in progress - 55% completed- work in progress under state plan | Kollam Project HD |