Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jul 2021 4 LL OHSR : works for last lift sidewall is completed on 21.7.2021... Pumping main : interconnection works at tank site in progress...Supply of pump sets :Not supplied Kollam Project HD
22 Jul 2021 4 LL OHSR : works for last lift sidewall is completed on 21.7.2021... Pumping main : interconnection works at tank site in progress...Supply of pump sets :Not supplied Kollam Project HD
17 Jul 2021 4 LL OHSR : works for last lift sidewall is in progress ...proposed RCC work is on 19.7.2021 Pumping main : only interconnection works pending Supply of pump sets : contractor assured to supply with I. One week Kollam Project HD
16 Jul 2021 Work in progress...( No work tody...due to heavy rain)works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done Kollam Project HD
14 Jul 2021 Work in progress...works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done Kollam Project HD
13 Jul 2021 Work in progress...works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done Kollam Project HD
12 Jul 2021 works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done Kollam Project HD
10 Jul 2021 works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done Kollam Project HD
07 Jul 2021 for 4LL OHSR- Side wall third lift works in progress....... 200mm Pumping main - 5100m/5140m completed, only intercnnection works pending.........20HP pumps sets to be supplied.... Kollam Project HD
06 Jul 2021 Side wall third lift works in progress Kollam Project HD