| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jul 2021 | 4 LL OHSR : works for last lift sidewall is completed on 21.7.2021... Pumping main : interconnection works at tank site in progress...Supply of pump sets :Not supplied | Kollam Project HD | |
| 22 Jul 2021 | 4 LL OHSR : works for last lift sidewall is completed on 21.7.2021... Pumping main : interconnection works at tank site in progress...Supply of pump sets :Not supplied | Kollam Project HD | |
| 17 Jul 2021 | 4 LL OHSR : works for last lift sidewall is in progress ...proposed RCC work is on 19.7.2021 Pumping main : only interconnection works pending Supply of pump sets : contractor assured to supply with I. One week | Kollam Project HD | |
| 16 Jul 2021 | Work in progress...( No work tody...due to heavy rain)works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done | Kollam Project HD | |
| 14 Jul 2021 | Work in progress...works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done | Kollam Project HD | |
| 13 Jul 2021 | Work in progress...works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done | Kollam Project HD | |
| 12 Jul 2021 | works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done | Kollam Project HD | |
| 10 Jul 2021 | works upto 3.65m completed OHSR side wall ( third lift) ....works for pumping main 5100m/5140..only interconnection works -pending due to ---the alignment may be fixed only after errecting pumpsets....pump set supply - not done | Kollam Project HD | |
| 07 Jul 2021 | for 4LL OHSR- Side wall third lift works in progress....... 200mm Pumping main - 5100m/5140m completed, only intercnnection works pending.........20HP pumps sets to be supplied.... | Kollam Project HD | |
| 06 Jul 2021 | Side wall third lift works in progress | Kollam Project HD |