| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 May 2021 | Work in slow progress.... Materials shortage due to lock down restrictions and heavy rain.... For ohsr ...works for reinforcement and shuttering for floor beam cum floor slab in progress | Kollam Project HD | |
| 11 May 2021 | Work in progress.... Materials shortage due to lock down restrictions.... For ohsr ...works for reinforcement and shuttering for floor beam cum floor slab in progress | Kollam Project HD | |
| 05 May 2021 | work for floor beam and floor slab in progress- shuttering and reinforcement work in progress. For pumping main - permission from the Jila panchayath obtained for laying balance portion | Kollam Project HD | |
| 16 Apr 2021 | pillar rising works upto floor beam completed and works for floor beam in progress | Kollam Project HD | |
| 09 Apr 2021 | Deshuttering works completed...and works for laying pipeline works almost completed...chamber works in progress | Kollam Project HD | |
| 03 Apr 2021 | works up to brace beam 3 rd completed and de shuttering in process | Kollam Project HD | |
| 31 Mar 2021 | RCC for 3rd beam work is proposed on 1.04.2021 | Kollam Project HD | |
| 29 Mar 2021 | Works upto bottom of 3 brace beam completed and shuttering and reinforcement works for 3 rd brace in progress | Kollam Project HD | |
| 26 Mar 2021 | Works upto bottom of 3 brace beam completed and shuttering and reinforcement works for 3 rd brace in progress | Kollam Project HD | |
| 24 Mar 2021 | For pipe laying permission is not granted along concrete cutting near cherkulam Masjid road and the ittiva grama panchayath - given permission along the drain nearby....for ohsr shuttering works started for 3 rs brace | Kollam Project HD |