| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 535 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 18 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 15 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 12 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 09 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 06 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 03 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 30 Apr 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 27 Apr 2024 | Pipe laid 10000 m out of 12000 m and FHTC 480 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 23 Apr 2024 | Pipe laid 10000 m out of 12000 m and FHTC 480 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 |