Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 535 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
18 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
15 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
12 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
09 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
06 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
03 May 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
30 Apr 2024 | Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
27 Apr 2024 | Pipe laid 10000 m out of 12000 m and FHTC 480 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
23 Apr 2024 | Pipe laid 10000 m out of 12000 m and FHTC 480 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 |