| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 11 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 08 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 05 Jun 2024 | Pipe laid 11250 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 02 Jun 2024 | Pipe laid 11250 m out of 12000 m and FHTC 665Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 30 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 665Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 27 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 660Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 27 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 540Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 24 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 540Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 24 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 535 Nos out of 760 Nos completed. | Kannur WS Sn AE 2 |