Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
11 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
08 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
05 Jun 2024 | Pipe laid 11250 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
02 Jun 2024 | Pipe laid 11250 m out of 12000 m and FHTC 665Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
30 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 665Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
27 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 660Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
27 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 540Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
24 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 540Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
24 May 2024 | Pipe laid 11250 m out of 12000 m and FHTC 535 Nos out of 760 Nos completed. | Kannur WS Sn AE 2 |