| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Oct 2024 | Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable | Kannur WS Sn AE 2 | |
| 08 Oct 2024 | Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable | Kannur WS Sn AE 2 | |
| 05 Oct 2024 | Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable | Kannur WS Sn AE 2 | |
| 02 Oct 2024 | Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable | Kannur WS Sn AE 2 | |
| 29 Sep 2024 | Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable | Kannur WS Sn AE 2 | |
| 26 Sep 2024 | Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable | Kannur WS Sn AE 2 | |
| 23 Sep 2024 | Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable | Kannur WS Sn AE 2 | |
| 20 Sep 2024 | ipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed | Kannur WS Sn AE 2 | |
| 17 Sep 2024 | Pipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed | Kannur WS Sn AE 2 | |
| 14 Sep 2024 | Pipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed | Kannur WS Sn AE 2 |