Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Jul 2024 Pipe laid 11800 m out of 12000 m and FHTC 720 Nos out of 740 Nos completed. Kannur WS Sn AE 2
11 Jul 2024 Pipe laid 11800 m out of 12000 m and FHTC 678Nos out of 740 Nos completed. Kannur WS Sn AE 2
08 Jul 2024 Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. Kannur WS Sn AE 2
05 Jul 2024 Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. Kannur WS Sn AE 2
02 Jul 2024 Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. Kannur WS Sn AE 2
29 Jun 2024 Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. Kannur WS Sn AE 2
26 Jun 2024 Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. Kannur WS Sn AE 2
23 Jun 2024 Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. Kannur WS Sn AE 2
20 Jun 2024 Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. Kannur WS Sn AE 2
17 Jun 2024 Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. Kannur WS Sn AE 2