| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 720 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 11 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 678Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 08 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 05 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 02 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 29 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 26 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 23 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 20 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
| 17 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 |