Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 720 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
11 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 678Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
08 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
05 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
02 Jul 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
29 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
26 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
23 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
20 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 | |
17 Jun 2024 | Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed. | Kannur WS Sn AE 2 |