Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Jul 2025 | 111000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
01 Jul 2025 | 110000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
27 Jun 2025 | 109000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
23 Jun 2025 | 108000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
19 Jun 2025 | 108000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
16 Jun 2025 | 107000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
12 Jun 2025 | 106000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
09 Jun 2025 | 106000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
05 Jun 2025 | 105000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
03 Jun 2025 | 104000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 |