Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jan 2025 | 97000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
24 Jan 2025 | 97000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
20 Jan 2025 | 97000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
16 Jan 2025 | 96000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
10 Jan 2025 | 94500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
08 Jan 2025 | 94500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
04 Jan 2025 | 94500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
31 Dec 2024 | 94000 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
26 Dec 2024 | 93500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
24 Dec 2024 | 93500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 |