Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Mar 2025 100000 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
05 Mar 2025 99000 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
27 Feb 2025 98300 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
22 Feb 2025 97500 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
18 Feb 2025 97500 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
15 Feb 2025 97500 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
11 Feb 2025 97500 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
06 Feb 2025 97000 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
05 Feb 2025 97000 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2
01 Feb 2025 97000 m pipe laid and 1150 HTC given Koothuparamba Proj AE 2