Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Sep 2024 | 87000m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
04 Sep 2024 | 87000m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
29 Aug 2024 | 87000m pipe laid and 945 HTC given | Koothuparamba Proj AE 2 | |
22 Aug 2024 | 87000m pipe laid and 945 HTC given | Koothuparamba Proj AE 2 | |
16 Aug 2024 | 87000m pipe laid and 945 HTC given | Koothuparamba Proj AE 2 | |
09 Aug 2024 | 87000m pipe laid and 945 HTC given | Koothuparamba Proj AE 2 | |
07 Aug 2024 | 87000m pipe laid and 945 HTC given | Koothuparamba Proj AE 2 | |
02 Aug 2024 | 86000m pipe laid and 945 HTC given | Koothuparamba Proj AE 2 | |
27 Jul 2024 | 86000m pipe laid and 945 HTC given | Koothuparamba Proj AE 2 | |