| Kollam WS Sn 2 - AE |
| Date: 24/06/2023 |
Work has been completed | 100% Completed
100 % completed
| Kollam WS Sn 2 - AE |
| Date: 22/06/2023 |
Work in progress | 98% Completed
Pipe laying work completed. Restoration of concrete to be done
| Kollam WS Sn 2 - AE |
| Date: 20/06/2023 |
Work in progress | 96% Completed
96% completed, Pipe laying cannot possible in water logged area due to rain .
| Kollam WS Sn 2 - AE |
| Date: 16/06/2023 |
Work in progress | 96% Completed
96%completed
| Kollam WS Sn 2 - AE |
| Date: 12/06/2023 |
Work in progress | 96% Completed
96 % completed
| Kollam WS Sn 2 - AE |
| Date: 09/06/2023 |
Work in progress | 90% Completed
90 % completed
| Kollam WS Sn 2 - AE |
| Date: 07/06/2023 |
Work in progress | 30% Completed
work started today morning.
| Kollam WS Sn 2 - AE |
| Date: 05/06/2023 |
Work in progress | 0% Completed
Site handed over and work will start soon.
| Kollam WS Sn 2 - AE |
| Date: 01/06/2023 |
Work in progress | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 29/05/2023 |
Work in progress | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 24/05/2023 |
Work in progress | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 22/05/2023 |
Work has started | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 19/05/2023 |
Work has started | 0% Completed
Tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 15/05/2023 |
Work has started | 0% Completed
Waiting for tested pipe
| Kollam WS Sn 2 - AE |
| Date: 11/05/2023 |
Work has started | 0% Completed
LOA prepared and sent to the contractor
| Kollam WS Sn 2 - AE |
| Date: 10/05/2023 |
Work has started | 0% Completed
LOA prepared and sent to the contractor