| Project | DEPOSIT-QWSS in Kollam -: Urban Agglomaration-Extension of 90mm and 63mm PVC pipe line at Div No 5 Vallikeezhu.- Pipeline Work |
|---|---|
| Project Code | KLMDEPO032314033P1 |
| Type | Package |
| Main Project | DEPOSIT-QWSS in Kollam -: Urban Agglomaration-Extension of 90mm and 63mm PVC pipe line at Div No 5 Vallikeezhu.- Pipeline Work |
| Funding Agency | DEPO |
| Category | Urban Water Supply Scheme – Others |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | DEPOSIT-QWSS in Kollam -: Urban Agglomaration-Extension of 90mm and 63mm PVC pipe line at Div No 5 Vallikeezhu.- Pipeline Work |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 573520 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/8555/2023_26_1_1 |
| Technical specification | extension of 90mm and 63mm PVC pipe line |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 23/03/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 10 Jun 2023 |
| Expected date of Completion | 31/05/2023 |
| TS Date | 10 Apr 2023 |
|---|---|
| Estimate Approval | 23 Mar 2023 |
| NIT Approval | 10 Apr 2023 |
| Tender Closing | 19 Apr 2023 |
| Technichal Pre-Qualification | 19 Apr 2023 |
| Price bid opening | 20 Apr 2023 |
| Workorder Date | 28 Apr 2023 |
|---|---|
| NA | 10 May 2023 |
| Kollam WS Sn 2 - AE |
| Date: 24/06/2023 |
Work has been completed | 100% Completed
100 % completed.
| Kollam WS Sn 2 - AE |
| Date: 22/06/2023 |
Work in progress | 98% Completed
Pipe laying work completed. Restoration of concrete to be done .