| Vadanappilly AE |
| Date: 19/09/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work including Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed. Due to PWD excavation ban no works ongoing
| Vadanappilly AE |
| Date: 15/07/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work including Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed. Due to PWD excavation ban no works ongoing
| Vadanappilly AE |
| Date: 08/07/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work including Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed. Due to PWD excavation ban no works ongoing
| Vadanappilly AE |
| Date: 01/07/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 16/06/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 08/06/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 04/06/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 26/05/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 20/05/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 13/05/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 04/05/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 21/04/2026 |
Work in progress | 50% Completed
GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed
| Vadanappilly AE |
| Date: 02/03/2026 |
Work in progress | 45% Completed
300mm pipe laying at talikulam panchayth road in progress, GSB & WMM road restoration work ongoing. Pipe laying 500mm DI - 2868m & 400mm DI - 2282m completed
| Vadanappilly AE |
| Date: 30/01/2026 |
Work in progress | 30% Completed
Work in progress .500mm DI - 2868m & 400mm DI - 2282m
| Vadanappilly AE |
| Date: 07/01/2026 |
Work in progress | 30% Completed
500mm DI - 2868m & 400mm DI - 2282m