KIIFB-KIIFB Project:TRAN-10 :WRD005-127 - CWSS to Nattika Firka-Replacing 500mm &400mm premo pipe with 600mm, 500mm & 400mm DI K9 pipe from Valapad - Sethukulam to Vadanappally Ganeshamangalam sump under P . H. Section Vadanappally.

Project KIIFB-KIIFB Project:TRAN-10 :WRD005-127 - CWSS to Nattika Firka-Replacing 500mm &400mm premo pipe with 600mm, 500mm & 400mm DI K9 pipe from Valapad - Sethukulam to Vadanappally Ganeshamangalam sump under P . H. Section Vadanappally.
Project Code TCRKIIFB04181359P7
Type Package
Main Project KIIFB -Project-(TRAN2-WRD005-127):Replacement of Transmission Mains in Thrissur Circle
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-KIIFB Project:TRAN-10 :WRD005-127 - CWSS to Nattika Firka-Replacing 500mm &400mm premo pipe with 600mm, 500mm & 400mm DI K9 pipe from Valapad - Sethukulam to Vadanappally Ganeshamangalam sump under P . H. Section Vadanappally.
Status On-going
District Thrissur
Executing Office Vadanappalli Sn
Agreement Number
Agreement Date
TS Amount (Rs) 264400000
TS Number WRD/KWA-CE(CR)/EST_TS/894/2022_26_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/06/2023
Scheduled date of Completion as per agreement 15 Feb 2026
Expected date of Completion Date is not specified

Processing Dates

TS Date 24 Aug 2023

Approval Dates

Workorder Date 16 Jun 2025
NA 14 Jul 2025

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vadanappilly AE
Date: 19/09/2026

Work in progress | 50% Completed

GSB & WMM road restoration work including Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed. Due to PWD excavation ban no works ongoing.

Vadanappilly AE
Date: 15/07/2026

Work in progress | 50% Completed

GSB & WMM road restoration work including Pipe laying 500mm DI - 3550m, 400mm DI - 2550m , 300mm - 341m completed. Due to PWD excavation ban no works ongoing.