| Oachira AE |
| Date: 12/05/2025 |
| Oachira AE |
| Date: 08/05/2025 |
Work in progress | 70% Completed
Work started on 27/04/2025. Laying of 63 mm PVC pipe (total length 70 m) and interconnection work completed. Re-concreting ongoing.
| Oachira AE |
| Date: 05/05/2025 |
| Oachira AE |
| Date: 02/05/2025 |
Work in progress | 40% Completed
Work started on 27/04/2025. Demolishing concrete completed. Pipe laying and interconnection work ongoing.
| Oachira AE |
| Date: 29/04/2025 |
Work in progress | 40% Completed
Work started on 27/04/2025. Demolishing concrete completed. Pipe laying and interconnection work ongoing.
| Oachira AE |
| Date: 28/04/2025 |
Work in progress | 40% Completed
Work started on 27/04/2025. Demolishing concrete completed. Pipe laying and interconnection work ongoing.
| Oachira AE |
| Date: 25/04/2025 |
Work in progress | 0% Completed
Work not started yet. Letter given to the contractor for starting work
| Oachira AE |
| Date: 24/04/2025 |
Work has started | 0% Completed
Work not started yet. Letter given to the contractor for starting work
| Oachira AE |
| Date: 22/04/2025 |
Work in progress | 0% Completed
Agreement executed on 15/03/2023, Site hand over on 24/03/2023
| Oachira AE |
| Date: 15/04/2025 |
Work in progress | 0% Completed
Agreement executed on 15/03/2023, Site hand over on 24/03/2023
| Oachira AE |
| Date: 10/04/2025 |
Work in progress | 0% Completed
Agreement executed on 15/03/2023, Site hand over on 24/03/2023
| Oachira AE |
| Date: 05/04/2025 |
Work in progress | 0% Completed
Agreement executed on 15/03/2023, Site hand over on 24/03/2023
| Oachira AE |
| Date: 01/04/2025 |
Work in progress | 0% Completed
Agreement executed on 15/03/2023, Site hand over on 24/03/2023
| Oachira AE |
| Date: 29/03/2025 |
Work has started | 0% Completed
Agreement executed on 15/03/2023, Site hand over on 24/03/2023