DEPOSIT-CWSS to Karunagappally Municipality-Extension of Pipe line from Puthenpurathara to Kannethara padinjare bhagom with 63mm PVC 6 Kg/cm2 pipe in Division 27 of Karunagappally Municipality.-Pipeline Work

Project DEPOSIT-CWSS to Karunagappally Municipality-Extension of Pipe line from Puthenpurathara to Kannethara padinjare bhagom with 63mm PVC 6 Kg/cm2 pipe in Division 27 of Karunagappally Municipality.-Pipeline Work
Project Code KLMDEPO012517247P1
Type Package
Main Project DEPOSIT-CWSS to Karunagappally Municipality-Extension of Pipe line from Puthenpurathara to Kannethara padinjare bhagom with 63mm PVC 6 Kg/cm2 pipe in Division 27 of Karunagappally Municipality.-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-CWSS to Karunagappally Municipality-Extension of Pipe line from Puthenpurathara to Kannethara padinjare bhagom with 63mm PVC 6 Kg/cm2 pipe in Division 27 of Karunagappally Municipality.-Pipeline Work
Status Completed
District Kollam
Executing Office Oachira PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 104400
TS Number WRD/KWA-CE(SR)/EST_TS/22017/2024_26_1_1
Technical specification 63 mm PVC pipe 6 kg/cm2

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/03/2025
Scheduled date of Completion as per agreement 23 May 2025
Expected date of Completion 23/05/2025

Processing Dates

TS Date 28 Jan 2025
Estimate Approval 28 Jan 2025
NIT Approval 28 Jan 2025
Tender Closing 24 Feb 2025
Technichal Pre-Qualification 24 Feb 2025
Price bid opening 25 Feb 2025

Approval Dates

Workorder Date 06 Mar 2025
NA 15 Mar 2025

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Oachira AE
Date: 12/05/2025

Work has been completed | 100% Completed

Work completed on 11/05/2025..

Attached images

img

Oachira AE
Date: 08/05/2025

Work in progress | 70% Completed

Work started on 27/04/2025. Laying of 63 mm PVC pipe (total length 70 m) and interconnection work completed. Re-concreting ongoing..