| Project | DEPOSIT-CWSS to Karunagappally Municipality-Extension of Pipe line from Puthenpurathara to Kannethara padinjare bhagom with 63mm PVC 6 Kg/cm2 pipe in Division 27 of Karunagappally Municipality.-Pipeline Work |
|---|---|
| Project Code | KLMDEPO012517247P1 |
| Type | Package |
| Main Project | DEPOSIT-CWSS to Karunagappally Municipality-Extension of Pipe line from Puthenpurathara to Kannethara padinjare bhagom with 63mm PVC 6 Kg/cm2 pipe in Division 27 of Karunagappally Municipality.-Pipeline Work |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | DEPOSIT-CWSS to Karunagappally Municipality-Extension of Pipe line from Puthenpurathara to Kannethara padinjare bhagom with 63mm PVC 6 Kg/cm2 pipe in Division 27 of Karunagappally Municipality.-Pipeline Work |
| Status | Completed |
| District | Kollam |
| Executing Office | Oachira PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 104400 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/22017/2024_26_1_1 |
| Technical specification | 63 mm PVC pipe 6 kg/cm2 |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 24/03/2025 |
|---|---|
| Scheduled date of Completion as per agreement | 23 May 2025 |
| Expected date of Completion | 23/05/2025 |
| TS Date | 28 Jan 2025 |
|---|---|
| Estimate Approval | 28 Jan 2025 |
| NIT Approval | 28 Jan 2025 |
| Tender Closing | 24 Feb 2025 |
| Technichal Pre-Qualification | 24 Feb 2025 |
| Price bid opening | 25 Feb 2025 |
| Workorder Date | 06 Mar 2025 |
|---|---|
| NA | 15 Mar 2025 |
| Oachira AE |
| Date: 12/05/2025 |
| Oachira AE |
| Date: 08/05/2025 |
Work in progress | 70% Completed
Work started on 27/04/2025. Laying of 63 mm PVC pipe (total length 70 m) and interconnection work completed. Re-concreting ongoing..