Piravam Project Sub Dn AE 2
Date: 27/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 26/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 24/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 21/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 13/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 03/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 21/05/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 17/05/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 14/05/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 08/05/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.

Piravam Project Sub Dn AE 2
Date: 06/05/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed .

Piravam Project Sub Dn AE 2
Date: 27/04/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site column work in progress.

Piravam Project Sub Dn AE 2
Date: 20/04/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site column work in progress.

Attached images

img img

Piravam Project Sub Dn AE 2
Date: 15/04/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site column work in progress.

Piravam Project Sub Dn AE 2
Date: 06/04/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site column work in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 27/03/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site foundation work in progress.

Attached images

img img

Piravam Project Sub Dn AE 2
Date: 19/03/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site foundation work in progress. Pipe line mapping in progress.

Piravam Project Sub Dn AE 2
Date: 12/03/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site reinforcement work in progress. Pipe line mapping in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 01/03/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site setout completed. Pipe line mapping in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 26/02/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site setout completed.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 20/02/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site setout completed.

Piravam Project Sub Dn AE 2
Date: 14/02/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site setout completed.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 13/02/2024

Work in progress | 25% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site setout completed.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 07/02/2024

Work in progress | 12% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site setout completed.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 03/02/2024

Work in progress | 12% Completed

Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress.

Attached images

img img

Piravam Project Sub Dn AE 2
Date: 29/01/2024

Work in progress | 12% Completed

Pipe laying 45 km completed & 30 nos fhtcs given.. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 23/01/2024

Work in progress | 11% Completed

Pipe laying 45 km completed & 30 nos fhtcs given.. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress.

Piravam Project Sub Dn AE 2
Date: 16/01/2024

Work in progress | 11% Completed

Pipe laying 45 km completed & 30 nos fhtcs given.. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress.

Attached images

img img

Piravam Project Sub Dn AE 2
Date: 09/01/2024

Work in progress | 10% Completed

Pipe laying 30 km completed. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress.

Piravam Project Sub Dn AE 2
Date: 04/01/2024

Work in progress | 10% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 18/12/2023

Work in progress | 9% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress. sump shutter work and pump house brick work, stair case work on ongoing.

Attached images

img img img img img img img img

Piravam Project Sub Dn AE 2
Date: 11/12/2023

Work in progress | 9% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress. sump shutter work and pump house brick work, stair case work on ongoing.

Attached images

img img img img

Piravam Project Sub Dn AE 2
Date: 06/12/2023

Work in progress | 9% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Attached images

img img

Piravam Project Sub Dn AE 2
Date: 30/11/2023

Work in progress | 9% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 27/11/2023

Work in progress | 9% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 23/11/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 18/11/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 15/11/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Attached images

img img img img img

Piravam Project Sub Dn AE 2
Date: 13/11/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 07/11/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 02/11/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 01/11/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 26/10/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 17/10/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 12/10/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 10/10/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 07/10/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress

Piravam Project Sub Dn AE 2
Date: 06/10/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 04/10/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 30/09/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 27/09/2023

Work in progress | 8% Completed

Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.

Piravam Project Sub Dn AE 2
Date: 23/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed. Construction of tank at konnanpara site in progress.

Piravam Project Sub Dn AE 2
Date: 19/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed. Construction of tank at konnanpara site in progress.

Piravam Project Sub Dn AE 2
Date: 16/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed. Construction of tank at konnanpara site in progress.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 15/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed.

Piravam Project Sub Dn AE 2
Date: 14/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 13/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed.

Piravam Project Sub Dn AE 2
Date: 11/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed.

Piravam Project Sub Dn AE 2
Date: 07/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed.

Attached images

img

Piravam Project Sub Dn AE 2
Date: 05/09/2023

Work in progress | 5% Completed

Design of of tank completed ,pipe laying 16 km completed.

Piravam Project Sub Dn AE 2
Date: 02/09/2023

Work in progress | 5% Completed

design of of tank completed ,pipe laying 16 km completed

Piravam Project Sub Dn AE 2
Date: 01/09/2023

Work in progress | 5% Completed

design of of tank completed ,pipe laying 16 km completed

Attached images

img img

Piravam Project Sub Dn AE 2
Date: 26/08/2023

Work in progress | 5% Completed

design of of tank completed ,pipe laying 16 km completed

Piravam Project Sub Dn AE 2
Date: 24/08/2023

Work in progress | 1% Completed

OHSR &GLSR work started. PVC pipe supplied