Piravam Project Sub Dn AE 2 |
Date: 27/06/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 26/06/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 24/06/2024 |
Piravam Project Sub Dn AE 2 |
Date: 21/06/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 13/06/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 03/06/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 21/05/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 17/05/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 14/05/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 08/05/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
Piravam Project Sub Dn AE 2 |
Date: 06/05/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed .
Piravam Project Sub Dn AE 2 |
Date: 27/04/2024 |
Work in progress | 25% Completed
Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site column work in progress.
Piravam Project Sub Dn AE 2 |
Date: 20/04/2024 |
Piravam Project Sub Dn AE 2 |
Date: 15/04/2024 |
Work in progress | 25% Completed
Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site column work in progress.
Piravam Project Sub Dn AE 2 |
Date: 06/04/2024 |
Piravam Project Sub Dn AE 2 |
Date: 27/03/2024 |
Piravam Project Sub Dn AE 2 |
Date: 19/03/2024 |
Work in progress | 25% Completed
Pipe laying 45 km completed & 30 nos fhtcs given. konthanpara tank workcompleted. sump cum pumphouse finishing work in progress. Vakkathipara tank site foundation work in progress. Pipe line mapping in progress.
Piravam Project Sub Dn AE 2 |
Date: 12/03/2024 |
Work in progress | 25% Completed
Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site reinforcement work in progress. Pipe line mapping in progress.
Attached images
Piravam Project Sub Dn AE 2 |
Date: 01/03/2024 |
Piravam Project Sub Dn AE 2 |
Date: 26/02/2024 |
Piravam Project Sub Dn AE 2 |
Date: 20/02/2024 |
Work in progress | 25% Completed
Pipe laying 45 km completed & 30 nos fhtcs given. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress. Vakkathipara tank site setout completed.
Piravam Project Sub Dn AE 2 |
Date: 14/02/2024 |
Piravam Project Sub Dn AE 2 |
Date: 13/02/2024 |
Piravam Project Sub Dn AE 2 |
Date: 07/02/2024 |
Piravam Project Sub Dn AE 2 |
Date: 03/02/2024 |
Piravam Project Sub Dn AE 2 |
Date: 29/01/2024 |
Piravam Project Sub Dn AE 2 |
Date: 23/01/2024 |
Work in progress | 11% Completed
Pipe laying 45 km completed & 30 nos fhtcs given.. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress.
Piravam Project Sub Dn AE 2 |
Date: 16/01/2024 |
Piravam Project Sub Dn AE 2 |
Date: 09/01/2024 |
Work in progress | 10% Completed
Pipe laying 30 km completed. konnanpara tank work in progress, plastering work in progress. sump cum pumphouse roof slab steel work in progress.
Piravam Project Sub Dn AE 2 |
Date: 04/01/2024 |
Work in progress | 10% Completed
Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 18/12/2023 |
Piravam Project Sub Dn AE 2 |
Date: 11/12/2023 |
Piravam Project Sub Dn AE 2 |
Date: 06/12/2023 |
Piravam Project Sub Dn AE 2 |
Date: 30/11/2023 |
Work in progress | 9% Completed
Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 27/11/2023 |
Work in progress | 9% Completed
Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 23/11/2023 |
Piravam Project Sub Dn AE 2 |
Date: 18/11/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 15/11/2023 |
Piravam Project Sub Dn AE 2 |
Date: 13/11/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 07/11/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 02/11/2023 |
Piravam Project Sub Dn AE 2 |
Date: 01/11/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 26/10/2023 |
Piravam Project Sub Dn AE 2 |
Date: 17/10/2023 |
Piravam Project Sub Dn AE 2 |
Date: 12/10/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 10/10/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 07/10/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress
Piravam Project Sub Dn AE 2 |
Date: 06/10/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 04/10/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 30/09/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 27/09/2023 |
Work in progress | 8% Completed
Design of of tank completed ,pipe laying 20 km completed. konnanpara tank work in progress, floor slab completed,work of side wall in progress.
Piravam Project Sub Dn AE 2 |
Date: 23/09/2023 |
Work in progress | 5% Completed
Design of of tank completed ,pipe laying 16 km completed. Construction of tank at konnanpara site in progress.
Piravam Project Sub Dn AE 2 |
Date: 19/09/2023 |
Work in progress | 5% Completed
Design of of tank completed ,pipe laying 16 km completed. Construction of tank at konnanpara site in progress.
Piravam Project Sub Dn AE 2 |
Date: 16/09/2023 |
Piravam Project Sub Dn AE 2 |
Date: 15/09/2023 |
Work in progress | 5% Completed
Design of of tank completed ,pipe laying 16 km completed.
Piravam Project Sub Dn AE 2 |
Date: 14/09/2023 |
Piravam Project Sub Dn AE 2 |
Date: 13/09/2023 |
Work in progress | 5% Completed
Design of of tank completed ,pipe laying 16 km completed.
Piravam Project Sub Dn AE 2 |
Date: 11/09/2023 |
Work in progress | 5% Completed
Design of of tank completed ,pipe laying 16 km completed.
Piravam Project Sub Dn AE 2 |
Date: 07/09/2023 |
Piravam Project Sub Dn AE 2 |
Date: 05/09/2023 |
Work in progress | 5% Completed
Design of of tank completed ,pipe laying 16 km completed.
Piravam Project Sub Dn AE 2 |
Date: 02/09/2023 |
Work in progress | 5% Completed
design of of tank completed ,pipe laying 16 km completed
Piravam Project Sub Dn AE 2 |
Date: 01/09/2023 |
Piravam Project Sub Dn AE 2 |
Date: 26/08/2023 |
Work in progress | 5% Completed
design of of tank completed ,pipe laying 16 km completed
Piravam Project Sub Dn AE 2 |
Date: 24/08/2023 |
Work in progress | 1% Completed
OHSR &GLSR work started. PVC pipe supplied