Jal Jeevan Mission (JJM)-WSS to Pothanicad Panchayath - Providing functional house hold connections in all houses -Package - II - Distribution components - Laying distribution lines,construction of OHSR's & Providing functional house hold connections
Project |
Jal Jeevan Mission (JJM)-WSS to Pothanicad Panchayath - Providing functional house hold connections in all houses -Package - II - Distribution components - Laying distribution lines,construction of OHSR's & Providing functional house hold connections |
Project Code |
EKMJJM092110918P2 |
Type |
Package |
Main Project |
JJM-WSS to Pothanikad and Pallarimangalam Panchayath in Ernakulam District
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-WSS to Pothanicad Panchayath - Providing functional house hold connections in all houses -Package - II - Distribution components - Laying distribution lines,construction of OHSR's & Providing functional house hold connections |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
376326570 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/16820/2022_5_1_1 |
Technical specification |
Distribution components & Tanks |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
15/06/2023 |
Scheduled date of Completion as per agreement |
15 Jun 2024 |
Expected date of Completion |
15/06/2024 |
Processing Dates
TS Date |
03 Feb 2023 |
Estimate Approval |
03 Feb 2023 |
NIT Approval |
04 Apr 2023 |
Tender Closing |
18 Apr 2023 |
Technichal Pre-Qualification |
15 Jun 2023 |
Price bid opening |
18 Apr 2023 |
Approval Dates
Workorder Date |
15 Jun 2023 |
NA |
15 Jun 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Piravam Project Sub Dn AE 2 |
Date: 27/06/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed..
Piravam Project Sub Dn AE 2 |
Date: 26/06/2024 |
Work in progress | 40% Completed
Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed.
.