Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-WSS to Pothanicad Panchayath - Providing functional house hold connections in all houses -Package - II - Distribution components - Laying distribution lines,construction of OHSR's & Providing functional house hold connections

Project Jal Jeevan Mission (JJM)-WSS to Pothanicad Panchayath - Providing functional house hold connections in all houses -Package - II - Distribution components - Laying distribution lines,construction of OHSR's & Providing functional house hold connections
Project Code EKMJJM092110918P2
Type Package
Main Project JJM-WSS to Pothanikad and Pallarimangalam Panchayath in Ernakulam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-WSS to Pothanicad Panchayath - Providing functional house hold connections in all houses -Package - II - Distribution components - Laying distribution lines,construction of OHSR's & Providing functional house hold connections
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 376326570
TS Number WRD/KWA-CE(CR)/EST_TS/16820/2022_5_1_1
Technical specification Distribution components & Tanks

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/06/2023
Scheduled date of Completion as per agreement 15 Jun 2024
Expected date of Completion 15/06/2024

Processing Dates

TS Date 03 Feb 2023
Estimate Approval 03 Feb 2023
NIT Approval 04 Apr 2023
Tender Closing 18 Apr 2023
Technichal Pre-Qualification 15 Jun 2023
Price bid opening 18 Apr 2023

Approval Dates

Workorder Date 15 Jun 2023
NA 15 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Piravam Project Sub Dn AE 2
Date: 27/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed..

Piravam Project Sub Dn AE 2
Date: 26/06/2024

Work in progress | 40% Completed

Pipe laying 65 km completed & 260 nos total connections given. konthanpara tank work 80% completed. sump cum pumphouse 75 % work completed. Vakkathipara tank site 18 % of work completed. .