Kollam Project HD
Date: 02/03/2021

Work has been completed | 100% Completed

laying works completed.

Kollam Project HD
Date: 26/02/2021

Work in progress | 96% Completed

33.245km laid out of 34.669 km, hydro testing, interconnection works and road restoration works in progress

Kollam Project HD
Date: 22/02/2021

Work in progress | 96% Completed

33.245km laid out of 34.669 km, hydro testing, interconnection works and road restoration works in progress.

Kollam Project HD
Date: 18/02/2021

Work in progress | 95% Completed

33.245km laid out of 34.669 km, hydro testing, interconnection works and road restoration works in progress.

Kollam Project HD
Date: 15/02/2021

Work in progress | 95% Completed

33.245km laid out of 34.669 km, hydro testing, interconnection works and road restoration works in progress

Kollam Project HD
Date: 05/02/2021

Work in progress | 95% Completed

33.245km laid out of 34.669 km , hydrotesting,interconnection works and road restoration works in progress

Kollam Project HD
Date: 02/02/2021

Work in progress | 95% Completed

33.216km laid out of 34.669km ,hydrotesting ,interconnection and road restoration in progress

Kollam Project HD
Date: 31/01/2021

Work in progress | 93% Completed

32.4km laid out of 34.669km,hydrotesting ,interconnection and road restoration in progress

Kollam Project HD
Date: 29/01/2021

Work in progress | 93% Completed

32.4km laid out of 34.669km,hydrotesting ,interconnection and road restoration in progress

Kollam Project HD
Date: 25/01/2021

Work in progress | 92% Completed

32.020km laid out of 34.669 km , hydrotesting,interconnection works and road restoration works in progress

Kollam Project HD
Date: 11/01/2021

Work in progress | 79% Completed

27.641km laid out of 34.669km ,,Hydrotesting ,interconnctions and GI works in progress

Kollam Project HD
Date: 10/12/2020

Work in progress | 50% Completed

19.6km laid out of 40km , hydrotesting ,GI interconnections , Road restoration works in progress

Kollam Project HD
Date: 15/08/2020

Work in progress | 48% Completed

18.8 km laid , Hydro testing of pipe line in progress ,GI pipe line works in progress

Kollam Project HD
Date: 10/07/2020

Work in progress | 47% Completed

18.8km laid and hydro testing of laid lines in progress

Kollam Project HD
Date: 01/07/2020

Work in progress | 46% Completed

18.8km laid ,hydrotesting in progress

Kollam Project HD
Date: 19/06/2020

Work in progress | 44% Completed

laying works in progress 17.861 kms pipe laid out of 44.42 Km

Kollam Project HD
Date: 18/06/2020

Work in progress | 2% Completed

17.861Km pipe laid