Angamaly AE |
Date: 04/03/2024 |
Work has been completed | 100% Completed
Work completed.
Angamaly AE |
Date: 28/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 26/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 24/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing
Angamaly AE |
Date: 23/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing
Angamaly AE |
Date: 22/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing
Angamaly AE |
Date: 19/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing
Angamaly AE |
Date: 15/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing
Angamaly AE |
Date: 01/02/2024 |
Work in progress | 90% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 31/01/2024 |
Work in progress | 90% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 30/01/2024 |
Work in progress | 90% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 29/01/2024 |
Work in progress | 90% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 27/01/2024 |
Work in progress | 90% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 25/01/2024 |
Work in progress | 90% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 24/01/2024 |
Work in progress | 90% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 23/01/2024 |
Work in progress | 89% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration , Concrete Works and Pressure filter works are progressing.
Angamaly AE |
Date: 22/01/2024 |
Work in progress | 88% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 20/01/2024 |
Work in progress | 87% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 19/01/2024 |
Work in progress | 86% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 18/01/2024 |
Work in progress | 85% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 17/01/2024 |
Work in progress | 84% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 16/01/2024 |
Work in progress | 83% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 12/01/2024 |
Work in progress | 80% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 11/01/2024 |
Work in progress | 79% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 10/01/2024 |
Work in progress | 78% Completed
300 mm DI pipe laying 3212.95 m completed. Road Restoration and Concrete Works are progressing.
Angamaly AE |
Date: 03/01/2024 |
Work in progress | 72% Completed
300 mm DI pipe laying 3212.95 m completed. 300 mm DI pipeline laying Progressing. DI gap closing and Valve fixing progressing.
Angamaly AE |
Date: 01/01/2024 |
Work in progress | 70% Completed
300 mm DI pipe laying 3209.65 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AEE |
Date: 29/12/2023 |
Work in progress | 68% Completed
300 mm DI pipe laying 3209.65 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 26/12/2023 |
Work in progress | 67% Completed
300 mm DI pipe laying 3207.65 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 23/12/2023 |
Work in progress | 66% Completed
300 mm DI pipe laying 3207.65 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 22/12/2023 |
Work in progress | 65% Completed
300 mm DI pipe laying 3206.45 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 21/12/2023 |
Work in progress | 64% Completed
300 mm DI pipe laying 3203.45 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 19/12/2023 |
Work in progress | 63% Completed
300 mm DI pipe laying 3199.80 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 18/12/2023 |
Work in progress | 62% Completed
300 mm DI pipe laying 3187.40 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 16/12/2023 |
Work in progress | 60% Completed
300 mm DI pipe laying 3187.40 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 15/12/2023 |
Work in progress | 59% Completed
300 mm DI pipe laying 3184.90 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 14/12/2023 |
Work in progress | 58% Completed
300 mm DI pipe laying 3183.34 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 13/12/2023 |
Work in progress | 57% Completed
300 mm DI pipe laying 3177.11 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 12/12/2023 |
Work in progress | 56% Completed
300 mm DI pipe laying 3172.41 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 11/12/2023 |
Work in progress | 55% Completed
300 mm DI pipe laying 3164.41 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 08/12/2023 |
Work in progress | 51% Completed
300 mm DI pipe laying 3157.03 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 06/12/2023 |
Work in progress | 50% Completed
300 mm DI pipe laying 3151.03 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 05/12/2023 |
Work in progress | 49% Completed
300 mm DI pipe laying 3147.63 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 04/12/2023 |
Work in progress | 48% Completed
300 mm DI pipe laying 3143.63 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 02/12/2023 |
Work in progress | 47% Completed
300 mm DI pipe laying 3080.58 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 01/12/2023 |
Work in progress | 46% Completed
300 mm DI pipe laying 3068.65 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 30/11/2023 |
Work in progress | 45% Completed
300 mm DI pipe laying 3061.93 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 29/11/2023 |
Work in progress | 44% Completed
300 mm DI pipe laying 3060.97 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 28/11/2023 |
Work in progress | 43% Completed
300 mm DI pipe laying 3029.97 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 27/11/2023 |
Work in progress | 42% Completed
300 mm DI pipe laying 3020.47 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 25/11/2023 |
Work in progress | 40% Completed
300 mm DI pipe laying 2,840.16 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 24/11/2023 |
Work in progress | 39% Completed
300 mm DI pipe laying 2,822.68 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 22/11/2023 |
Work in progress | 38% Completed
300 mm DI pipe laying 2,809.18 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 21/11/2023 |
Work in progress | 37% Completed
300 mm DI pipe laying 2,800.08 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 20/11/2023 |
Work in progress | 36% Completed
300 mm DI pipe laying 2,766.58 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing
Angamaly AE |
Date: 18/11/2023 |
Work in progress | 35% Completed
300 mm DI pipe laying 2,739.32 m completed. 300 mm DI pipeline laying Progressing. DI gap closing progressing.
Angamaly AE |
Date: 17/11/2023 |
Work in progress | 34% Completed
300 mm DI pipe laying 2,714.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 15/11/2023 |
Work in progress | 33% Completed
300 mm DI pipe laying 2,670.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 14/11/2023 |
Work in progress | 33% Completed
300 mm DI pipe laying 2,637.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 13/11/2023 |
Work in progress | 32% Completed
300 mm DI pipe laying 2,624.35 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 10/11/2023 |
Work in progress | 31% Completed
300 mm DI pipe laying 2,474.35 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 09/11/2023 |
Work in progress | 30% Completed
300 mm DI pipe laying 2,439.85 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 08/11/2023 |
Work in progress | 29% Completed
300 mm DI pipe laying 2372.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 07/11/2023 |
Work in progress | 28% Completed
300 mm DI pipe laying 2252.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 06/11/2023 |
Work in progress | 27% Completed
300 mm DI pipe laying 2167.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 04/11/2023 |
Work in progress | 26% Completed
300 mm DI pipe laying 2079.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 03/11/2023 |
Work in progress | 25% Completed
300 mm DI pipe laying 2024.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 01/11/2023 |
Work in progress | 25% Completed
300 mm DI pipe laying 1985.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 31/10/2023 |
Work in progress | 23% Completed
300 mm DI pipe laying 1936.15 m completed. 300 mm DI pipeline laying Progressing.
Angamaly AE |
Date: 30/10/2023 |
Work in progress | 23% Completed
300 mm DI pipe laying 1864.65 m completed. 300 mm DI pipeline laying Progressing.
Angamaly AE |
Date: 28/10/2023 |
Work in progress | 22% Completed
300 mm DI pipe laying 1754.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 27/10/2023 |
Work in progress | 22% Completed
300 mm DI pipe laying 1629.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 26/10/2023 |
Work in progress | 22% Completed
300 mm DI pipe laying 1568.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 23/10/2023 |
Work in progress | 21% Completed
300 mm DI pipe laying 1534.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 22/10/2023 |
Work in progress | 21% Completed
300 mm DI pipe laying 1501.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 21/10/2023 |
Work in progress | 21% Completed
300 mm DI pipe laying 1440.15 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 20/10/2023 |
Work in progress | 20% Completed
300 mm DI pipe laying 1379.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 19/10/2023 |
Work in progress | 20% Completed
300 mm DI pipe laying 1343.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 18/10/2023 |
Work in progress | 15% Completed
300 mm DI pipe laying 1265.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 17/10/2023 |
Work in progress | 15% Completed
300 mm DI pipe laying 1265.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 16/10/2023 |
Work in progress | 15% Completed
300 mm DI pipe laying 1265.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 13/10/2023 |
Work in progress | 15% Completed
300 mm DI pipe laying 1265.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 12/10/2023 |
Work in progress | 12% Completed
300 mm DI pipe laying 1145.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 11/10/2023 |
Work in progress | 12% Completed
300 mm DI pipe laying 1145.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 10/10/2023 |
Work in progress | 12% Completed
300 mm DI pipe laying 959.65 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 07/10/2023 |
Work in progress | 11% Completed
300 mm DI pipe laying 759.5 m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 06/10/2023 |
Work in progress | 10% Completed
300 mm DI pipe laying 619m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 05/10/2023 |
Work in progress | 10% Completed
300 mm DI pipe laying 509.5m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 04/10/2023 |
Work in progress | 10% Completed
300 mm DI pipe laying 498.5m completed. 300 mm DI pipeline laying Progressing
Angamaly AE |
Date: 03/10/2023 |
Work in progress | 10% Completed
300 mm DI pipe laying 312.5m completed. 300 mm DI pipeline laying Progressing