Project | Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe.-Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe |
---|---|
Project Code | EKMJJM08203266P5 |
Type | Package |
Main Project | Jal Jeevan Mission- Multi Village Scheme - RWSS to Karukutty and Mookkannoor Panchayaths - Replacement of 315 mm PVC pipe to 300 mm DI K9 pipe, Extension of pipe line, Providing FHTC and allied works in Karukutty Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe.-Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe |
Status | On-going |
District | Ernakulam |
Executing Office | Angamaly Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 33800000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/9904/2022_26_1_1 Dated: 10-05-2023 |
Technical specification | |
Contractor | M B Pradeep (Mob: 9388024636) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 16 Feb 2024 |
Expected date of Completion | 16/02/2024 |
TS Date | 10 May 2023 |
---|---|
Estimate Approval | 10 May 2023 |
NIT Approval | 29 May 2023 |
Tender Closing | 06 Jun 2023 |
Technichal Pre-Qualification | 14 Jun 2023 |
Price bid opening | 07 Jun 2023 |
Workorder Date | 25 Jul 2023 |
---|---|
NA | 18 Aug 2023 |
Angamaly AE |
Date: 04/03/2024 |
Work has been completed | 100% Completed
Work completed..
Angamaly AE |
Date: 28/02/2024 |
Work in progress | 97% Completed
300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing..