Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe.-Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe

Project Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe.-Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe
Project Code EKMJJM08203266P5
Type Package
Main Project Jal Jeevan Mission- Multi Village Scheme - RWSS to Karukutty and Mookkannoor Panchayaths - Replacement of 315 mm PVC pipe to 300 mm DI K9 pipe, Extension of pipe line, Providing FHTC and allied works in Karukutty Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe.-Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe
Status On-going
District Ernakulam
Executing Office Angamaly Sn
Agreement Number
Agreement Date
TS Amount (Rs) 33800000
TS Number WRD/KWA-CE(CR)/EST_TS/9904/2022_26_1_1 Dated: 10-05-2023
Technical specification
Contractor M B Pradeep (Mob: 9388024636)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/08/2023
Scheduled date of Completion as per agreement 16 Feb 2024
Expected date of Completion 16/02/2024

Processing Dates

TS Date 10 May 2023
Estimate Approval 10 May 2023
NIT Approval 29 May 2023
Tender Closing 06 Jun 2023
Technichal Pre-Qualification 14 Jun 2023
Price bid opening 07 Jun 2023

Approval Dates

Workorder Date 25 Jul 2023
NA 18 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Angamaly AE
Date: 04/03/2024

Work has been completed | 100% Completed

Work completed..

Angamaly AE
Date: 28/02/2024

Work in progress | 97% Completed

300 mm DI pipe laying 3218.45 m completed. Road Restoration and Concrete Works are progressing..