Sulthan Bathery PH Sn - AE |
Date: 01/07/2024 |
Work in progress | 58% Completed
955nos HTC and 70 nos FHTC provided, No Work due to rain
Sulthan Bathery PH Sn - AE |
Date: 26/06/2024 |
Work in progress | 56% Completed
13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed, No Work due to rain
Sulthan Bathery PH Sn - AE |
Date: 18/06/2024 |
Work in progress | 56% Completed
13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed
Sulthan Bathery PH Sn - AE |
Date: 07/06/2024 |
Work in progress | 56% Completed
13 LL Ambalavayal ohsr hunch concrete on going
Sulthan Bathery PH Sn - AE |
Date: 30/05/2024 |
Work in progress | 55% Completed
13 LL Ambalavayal ohsr hunch concrete on going
Sulthan Bathery PH Dn EE |
Date: 22/05/2024 |
Work in progress | 54% Completed
13 LL Ambalavayal ohsr hunch concrete on going
Sulthan Bathery PH Sn - AE |
Date: 08/05/2024 |
Work in progress | 54% Completed
Ambalavayal OHSR - Base slab concrete completed
Sulthan Bathery PH Dn EE |
Date: 25/04/2024 |
Work in progress | 48% Completed
Ambalavayal 13LL GLSR , main base slab shuttering works completed , reinforcement works progress
Sulthan Bathery PH Sn - AE |
Date: 16/04/2024 |
Work in progress | 43% Completed
Total pipe laid 58.24 Km, 13LL Ambalavayal OHSR , Base Slab Shuttering and Reinforcement works progress
Sulthan Bathery PH Dn EE |
Date: 12/04/2024 |
Work in progress | 40% Completed
Total pipe laid 58.24 Km, 13LL Ambalavayal OHSR , Base Slab Shuttering and Reinforcement works progress , Column and beam works completed up to base level
Sulthan Bathery PH Dn EE |
Date: 01/04/2024 |
Work in progress | 40% Completed
1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 23/03/2024 |
Work in progress | 40% Completed
1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 15/03/2024 |
Work in progress | 40% Completed
1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 07/03/2024 |
Work in progress | 40% Completed
1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 28/02/2024 |
Work in progress | 40% Completed
1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 20/02/2024 |
Work in progress | 40% Completed
1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 12/02/2024 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 02/02/2024 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 25/01/2024 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 17/01/2024 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 06/01/2024 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 29/12/2023 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 21/12/2023 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 13/12/2023 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 05/12/2023 |
Work in progress | 20% Completed
Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.
Sulthan Bathery PH Dn EE |
Date: 02/12/2023 |
Work in progress | 15% Completed
33090 m pipe laid and 442 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 24/11/2023 |
Work in progress | 15% Completed
33090 m pipe laid and 442 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 16/11/2023 |
Work in progress | 10% Completed
33090 m pipe laid and 442 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 08/11/2023 |
Work in progress | 10% Completed
33090 m pipe laid and 442 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 30/10/2023 |
Work in progress | 5% Completed
15000 m pipe laid and 180 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 21/10/2023 |
Work in progress | 5% Completed
15000 m pipe laid and 180 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 13/10/2023 |
Work in progress | 5% Completed
15000 m pipe laid and 180 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 05/10/2023 |
Work in progress | 5% Completed
15000 m pipe laid and 180 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 27/09/2023 |
Work in progress | 5% Completed
15000 m pipe laid and 180 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 19/09/2023 |
Work in progress | 5% Completed
15000 m pipe laid and 180 HTC Provided.
Sulthan Bathery PH Dn EE |
Date: 11/09/2023 |
Work in progress | 5% Completed
15000 m pipe laid and 180 HTC Provided.
Sulthan Bathery PH Sn - AE |
Date: 01/09/2023 |
Sulthan Bathery PH Dn EE |
Date: 26/08/2023 |
Work in progress | 5% Completed
Site leveling for OHSR Ambalavayal.
Sulthan Bathery PH Dn EE |
Date: 17/08/2023 |
Work in progress | 5% Completed
Site leveling for OHSR Ambalavayal.
Sulthan Bathery PH Dn EE |
Date: 08/08/2023 |
Work in progress | 1% Completed
Site leveling for OHSR Ambalavayal.
Sulthan Bathery PH Dn EE |
Date: 31/07/2023 |
Work in progress | 1% Completed
Site leveling for OHSR Ambalavayal.
Sulthan Bathery PH Sn - AE |
Date: 22/07/2023 |
Sulthan Bathery PH Sn - AE |
Date: 15/07/2023 |
Work in progress | 1% Completed
Pipe supplied
Sulthan Bathery PH Dn EE |
Date: 10/07/2023 |
Work in progress | 1% Completed
Pipe supplied
Sulthan Bathery PH Sn - AE |
Date: 07/07/2023 |
Work in progress | 1% Completed
Pipe supplied
Sulthan Bathery PH Sn - AE |
Date: 30/06/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 24/06/2023 |
Sulthan Bathery PH Sn - AE |
Date: 19/06/2023 |
Work in progress | 1% Completed
Inauguration conducted on 19/06/2023
Sulthan Bathery PH Dn EE |
Date: 13/06/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 05/06/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 30/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 27/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Dn EE |
Date: 24/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 20/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Dn EE |
Date: 16/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Dn EE |
Date: 12/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Dn EE |
Date: 08/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 02/05/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 24/04/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Dn EE |
Date: 18/04/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Dn EE |
Date: 10/04/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Dn EE |
Date: 30/03/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 22/03/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 18/03/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 17/03/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 13/03/2023 |
Work in progress | 1% Completed
Pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 04/03/2023 |
Work in progress | 1% Completed
pipe supplied.
Sulthan Bathery PH Sn - AE |
Date: 01/03/2023 |
Work has started | 0% Completed
Agreement executed
Sulthan Bathery PH Sn - AE |
Date: 27/02/2023 |
Work has started | 0% Completed
Agreement executed
Sulthan Bathery PH Sn - AE |
Date: 24/02/2023 |
Work has started | 0% Completed
Agreement executed
Sulthan Bathery PH Sn - AE |
Date: 21/02/2023 |
Work has started | 0% Completed
Agreement executed
Sulthan Bathery PH Dn EE |
Date: 17/02/2023 |
Work in progress | 0% Completed
Agreement executed
Sulthan Bathery PH Dn EE |
Date: 15/02/2023 |
Work has started | 0% Completed
Awaiting Tender sanction from CE office.
Sulthan Bathery PH Sn - AE |
Date: 14/02/2023 |
Work has started | 0% Completed
Awaiting Tender sanction from CE office.
Sulthan Bathery PH Sn - AE |
Date: 09/02/2023 |
Work has started | 0% Completed
Awaiting Tender sanction from CE office.
Sulthan Bathery PH Sn - AE |
Date: 06/02/2023 |
Work has started | 0% Completed
Awaiting Tender sanction from CE office.
Sulthan Bathery PH Sn - AE |
Date: 01/02/2023 |
Work in progress | 0% Completed
Awaiting Tender sanction from CE office.
Sulthan Bathery PH Dn EE |
Date: 26/01/2023 |
Work has started | 0% Completed
Awaiting Tender sanction from CE office.
Sulthan Bathery PH Sn - AE |
Date: 23/01/2023 |
Work has started | 0% Completed
work not Started
Sulthan Bathery PH Sn - AE |
Date: 18/01/2023 |
Work has started | 0% Completed
work not Started
Sulthan Bathery PH Sn - AE |
Date: 16/01/2023 |
Work has started | 0% Completed
work not Started
Sulthan Bathery PH Sn - AE |
Date: 11/01/2023 |
Work has started | 0% Completed
work not Started
Sulthan Bathery PH Sn - AE |
Date: 06/01/2023 |
Work has started | 0% Completed
work not Started
Sulthan Bathery PH Sn - AE |
Date: 03/01/2023 |
Work has started | 0% Completed
work not Started
Sulthan Bathery PH Sn - AE |
Date: 31/12/2022 |
Work has started | 0% Completed
Work not started.
Sulthan Bathery PH Sn - AE |
Date: 28/12/2022 |
Work has started | 0% Completed
Tender opened.Under prequalification.
Sulthan Bathery PH Dn EE |
Date: 23/12/2022 |
Work has started | 0% Completed
Tender opened.Under prequalification.
Sulthan Bathery PH Dn EE |
Date: 15/12/2022 |
Work has started | 0% Completed
Tender opened.Under prequalification.
Sulthan Bathery PH Dn EE |
Date: 07/12/2022 |
Work has started | 0% Completed
Tender opened.Under prequalification.
Sulthan Bathery PH Dn EE |
Date: 25/11/2022 |
Work in progress | 0% Completed
Work tendered with due date 29-11-2022
Sulthan Bathery PH Dn EE |
Date: 20/10/2022 |
Work has started | 0% Completed
Estimate in PRICE 3 submitted for TS. Under scrutiny.