Sulthan Bathery PH Sn - AE
Date: 01/07/2024

Work in progress | 58% Completed

955nos HTC and 70 nos FHTC provided, No Work due to rain

Sulthan Bathery PH Sn - AE
Date: 26/06/2024

Work in progress | 56% Completed

13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed, No Work due to rain

Sulthan Bathery PH Sn - AE
Date: 18/06/2024

Work in progress | 56% Completed

13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed

Sulthan Bathery PH Sn - AE
Date: 07/06/2024

Work in progress | 56% Completed

13 LL Ambalavayal ohsr hunch concrete on going

Sulthan Bathery PH Sn - AE
Date: 30/05/2024

Work in progress | 55% Completed

13 LL Ambalavayal ohsr hunch concrete on going

Sulthan Bathery PH Dn EE
Date: 22/05/2024

Work in progress | 54% Completed

13 LL Ambalavayal ohsr hunch concrete on going

Sulthan Bathery PH Sn - AE
Date: 08/05/2024

Work in progress | 54% Completed

Ambalavayal OHSR - Base slab concrete completed

Sulthan Bathery PH Dn EE
Date: 25/04/2024

Work in progress | 48% Completed

Ambalavayal 13LL GLSR , main base slab shuttering works completed , reinforcement works progress

Sulthan Bathery PH Sn - AE
Date: 16/04/2024

Work in progress | 43% Completed

Total pipe laid 58.24 Km, 13LL Ambalavayal OHSR , Base Slab Shuttering and Reinforcement works progress

Sulthan Bathery PH Dn EE
Date: 12/04/2024

Work in progress | 40% Completed

Total pipe laid 58.24 Km, 13LL Ambalavayal OHSR , Base Slab Shuttering and Reinforcement works progress , Column and beam works completed up to base level

Sulthan Bathery PH Dn EE
Date: 01/04/2024

Work in progress | 40% Completed

1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 23/03/2024

Work in progress | 40% Completed

1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 15/03/2024

Work in progress | 40% Completed

1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 07/03/2024

Work in progress | 40% Completed

1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 28/02/2024

Work in progress | 40% Completed

1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 20/02/2024

Work in progress | 40% Completed

1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 12/02/2024

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 02/02/2024

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 25/01/2024

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 17/01/2024

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 06/01/2024

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 29/12/2023

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 21/12/2023

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 13/12/2023

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 05/12/2023

Work in progress | 20% Completed

Work in progress- 38050m Pipes laid. 1195 FHTCs and 170 HTC connections given.

Sulthan Bathery PH Dn EE
Date: 02/12/2023

Work in progress | 15% Completed

33090 m pipe laid and 442 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 24/11/2023

Work in progress | 15% Completed

33090 m pipe laid and 442 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 16/11/2023

Work in progress | 10% Completed

33090 m pipe laid and 442 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 08/11/2023

Work in progress | 10% Completed

33090 m pipe laid and 442 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 30/10/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 21/10/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 13/10/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 05/10/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 27/09/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 19/09/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Sulthan Bathery PH Dn EE
Date: 11/09/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Sulthan Bathery PH Sn - AE
Date: 01/09/2023

Work in progress | 5% Completed

15000 m pipe laid and 180 HTC Provided.

Attached images

img

Sulthan Bathery PH Dn EE
Date: 26/08/2023

Work in progress | 5% Completed

Site leveling for OHSR Ambalavayal.

Sulthan Bathery PH Dn EE
Date: 17/08/2023

Work in progress | 5% Completed

Site leveling for OHSR Ambalavayal.

Sulthan Bathery PH Dn EE
Date: 08/08/2023

Work in progress | 1% Completed

Site leveling for OHSR Ambalavayal.

Sulthan Bathery PH Dn EE
Date: 31/07/2023

Work in progress | 1% Completed

Site leveling for OHSR Ambalavayal.

Sulthan Bathery PH Sn - AE
Date: 22/07/2023

Work in progress | 1% Completed

Site leveling for OHSR Ambalavayal.

Attached images

img

Sulthan Bathery PH Sn - AE
Date: 15/07/2023

Work in progress | 1% Completed

Pipe supplied

Sulthan Bathery PH Dn EE
Date: 10/07/2023

Work in progress | 1% Completed

Pipe supplied

Sulthan Bathery PH Sn - AE
Date: 07/07/2023

Work in progress | 1% Completed

Pipe supplied

Sulthan Bathery PH Sn - AE
Date: 30/06/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 24/06/2023

Work in progress | 1% Completed

Inauguration conducted on 19/06/2023

Attached images

img

Sulthan Bathery PH Sn - AE
Date: 19/06/2023

Work in progress | 1% Completed

Inauguration conducted on 19/06/2023

Sulthan Bathery PH Dn EE
Date: 13/06/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 05/06/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 30/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 27/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Dn EE
Date: 24/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 20/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Dn EE
Date: 16/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Dn EE
Date: 12/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Dn EE
Date: 08/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 02/05/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 24/04/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Dn EE
Date: 18/04/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Dn EE
Date: 10/04/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Dn EE
Date: 30/03/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 22/03/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 18/03/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 17/03/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 13/03/2023

Work in progress | 1% Completed

Pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 04/03/2023

Work in progress | 1% Completed

pipe supplied.

Sulthan Bathery PH Sn - AE
Date: 01/03/2023

Work has started | 0% Completed

Agreement executed

Sulthan Bathery PH Sn - AE
Date: 27/02/2023

Work has started | 0% Completed

Agreement executed

Sulthan Bathery PH Sn - AE
Date: 24/02/2023

Work has started | 0% Completed

Agreement executed

Sulthan Bathery PH Sn - AE
Date: 21/02/2023

Work has started | 0% Completed

Agreement executed

Sulthan Bathery PH Dn EE
Date: 17/02/2023

Work in progress | 0% Completed

Agreement executed

Sulthan Bathery PH Dn EE
Date: 15/02/2023

Work has started | 0% Completed

Awaiting Tender sanction from CE office.

Sulthan Bathery PH Sn - AE
Date: 14/02/2023

Work has started | 0% Completed

Awaiting Tender sanction from CE office.

Sulthan Bathery PH Sn - AE
Date: 09/02/2023

Work has started | 0% Completed

Awaiting Tender sanction from CE office.

Sulthan Bathery PH Sn - AE
Date: 06/02/2023

Work has started | 0% Completed

Awaiting Tender sanction from CE office.

Sulthan Bathery PH Sn - AE
Date: 01/02/2023

Work in progress | 0% Completed

Awaiting Tender sanction from CE office.

Sulthan Bathery PH Dn EE
Date: 26/01/2023

Work has started | 0% Completed

Awaiting Tender sanction from CE office.

Sulthan Bathery PH Sn - AE
Date: 23/01/2023

Work has started | 0% Completed

work not Started

Sulthan Bathery PH Sn - AE
Date: 18/01/2023

Work has started | 0% Completed

work not Started

Sulthan Bathery PH Sn - AE
Date: 16/01/2023

Work has started | 0% Completed

work not Started

Sulthan Bathery PH Sn - AE
Date: 11/01/2023

Work has started | 0% Completed

work not Started

Sulthan Bathery PH Sn - AE
Date: 06/01/2023

Work has started | 0% Completed

work not Started

Sulthan Bathery PH Sn - AE
Date: 03/01/2023

Work has started | 0% Completed

work not Started

Sulthan Bathery PH Sn - AE
Date: 31/12/2022

Work has started | 0% Completed

Work not started.

Sulthan Bathery PH Sn - AE
Date: 28/12/2022

Work has started | 0% Completed

Tender opened.Under prequalification.

Sulthan Bathery PH Dn EE
Date: 23/12/2022

Work has started | 0% Completed

Tender opened.Under prequalification.

Sulthan Bathery PH Dn EE
Date: 15/12/2022

Work has started | 0% Completed

Tender opened.Under prequalification.

Sulthan Bathery PH Dn EE
Date: 07/12/2022

Work has started | 0% Completed

Tender opened.Under prequalification.

Sulthan Bathery PH Dn EE
Date: 25/11/2022

Work in progress | 0% Completed

Work tendered with due date 29-11-2022

Sulthan Bathery PH Dn EE
Date: 20/10/2022

Work has started | 0% Completed

Estimate in PRICE 3 submitted for TS. Under scrutiny.